Filter by category
Filter by Date
Cancellation - Possible intervention to manage power system security in SA region 10/05/2024
Cancellation - Possible intervention to manage power system security in SA region 10/05/2024
Refer Market Notice 116561
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1400 hrs 09/05/2024.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 0930 hrs 10/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event: Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer - Qld region.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event. AEMO considers the simultaneous trip of the following elements to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: Qld
Elements: Ross 275 kV SVC and Ross 275/132 kV No. 4 transformer
Duration: 1400 hrs 09/05/2024 until further notice
Constraint set(s) invoked:
Nil
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.116545 is cancelled at 1915 hrs 08/05/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 09/05/2024
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 09/05/2024 to 1800 hrs 09/05/2024.
The forecast capacity reserve requirement is 862 MW.
The minimum capacity reserve available is 721 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation - Possible intervention to manage power system security in SA region 09/05/2024
Cancellation - Possible intervention to manage power system security in SA region 09/05/2024
Refer Market Notice 116528
AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1400 hrs 08/05/2024.
Manager NEM Real Time Operations
Possible intervention to manage power system security in SA region
Possible intervention to manage power system security in SA region
The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 09/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 07/05/2024
Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 07/05/2024
Refer Market Notice 116510
The AEMO Intervention Event and all associated directions are cancelled from 0805 hrs 08/05/2024
Manager NEM Real Time Operations
Cancellation of a Non-Credible Contingency Event: Collinsville - Stoney Creek 7306 132KV LINE line and Collinsville - Newlands 7121 132KV LINE line in QLD1 due to Lightning.
Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.
Region: QLD1
Lines: Collinsville - Stoney Creek 7306 132KV LINE and Collinsville - Newlands 7121 132KV LINE
Cancellation time: 08/05/2024 01:09
Constraint set(s) revoked:
NONE
Refer AEMO Electricity Market Notice 116517
Auto-generated on behalf of Manager NEM Real Time Operations