116550ADMINISTERED PRICE CAP08/05/2024 07:45:12 PM

[EventId:197] AP STARTED for ENERGY in NSW1 at 08 May 2024 19:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1945 hrs on 08 May 2024

ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.

AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.

In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1955 hrs on 08 May 2024 and will continue through to the end of that trading day.

An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.

An administered floor price (AFP) of -600 $/MWh will apply to spot prices.

AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.

This is an AEMO autogenerated Market Notice.
     
116541MARKET INTERVENTION08/05/2024 02:02:29 PM

Cancellation - Possible intervention to manage power system security in SA region 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Possible intervention to manage power system security in SA region 09/05/2024

Refer Market Notice 116528

AEMO no longer foresees a possible requirement for intervention to manage power system security in SA region. The advice of possible intervention is cancelled from 1400 hrs 08/05/2024.

Manager NEM Real Time Operations
     
116528MARKET INTERVENTION08/05/2024 12:42:28 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0830 hrs 09/05/2024 will be inadequate to maintain a secure operating state in SA .
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA .

Manager NEM Real Time Operations
     
116523MARKET INTERVENTION08/05/2024 08:05:33 AM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 07/05/2024

Refer Market Notice 116510

The AEMO Intervention Event and all associated directions are cancelled from 0805 hrs 08/05/2024

Manager NEM Real Time Operations
     
116510MARKET INTERVENTION07/05/2024 03:14:19 PM

Direction - {{REGION:SA}} region {{DATE:07/05/2024}}

AEMO ELECTRICITY MARKET NOTICE.

Direction - {{REGION:SA}} region {{DATE:07/05/2024}}

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the {{REGION:SA}} region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending {{HRS:1605}} hrs on {{DATE:07/05/2024}}.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116508MARKET INTERVENTION07/05/2024 02:24:11 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116505

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 08/05/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 07/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116505MARKET INTERVENTION07/05/2024 01:04:36 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0900 hrs 08/05/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116497MARKET INTERVENTION06/05/2024 03:31:27 PM

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 06/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - Intervention trading intervals - Direction SA region 06/05/2024

Refer Market Notice 116492

The AEMO Intervention Event and all associated directions are cancelled from 1530 hrs 06/05/2024

Manager NEM Real Time Operations
     
116493MARKET INTERVENTION06/05/2024 01:12:59 PM

Possible intervention to manage power system security in SA Region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA Region

The synchronous generating units currently expected to be synchronised in SA from 0800 hrs 07/05/2024 will be inadequate to maintain sufficient system strength in SA and hence a secure operating state.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     