Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
Cancellation of Actual (LOR3) condition in the VIC region - 13/02/2024
The Actual LOR3 Condition in the VIC region advised in AEMO Electricity Market Notice No.114604 is cancelled at 1515 hrs 13/02/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Actual Lack Of Reserve Level 3 (LOR3) in the VIC region - 13/02/2024
Customer load shedding of non-interruptible load is occurring in the VIC region as a result of a shortfall of available capacity reserves.
An Actual LOR3 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the VIC region from 1420 hrs.
The Actual LOR3 condition is not forecast in Pre Dispatch.
The maximum load to be interrupted is up to 450 MW from 1420 hrs 13/02/2024
Manager NEM Real Time Operations
STPASA - Suspect Lack Of Reserve Level 3 (LOR3) in the QLD Region on 01/02/2024
AEMO considers that there are suspect Forecast LOR3 conditions for the QLD region for the following periods:
1. From 0900 hrs to 1000 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 38 MW at 0930 hrs.
2. From 1130 hrs to 1200 hrs 01/02/2024.
The maximum load (other than interruptible loads) forecast to be interrupted is 62 MW at 1130 hrs.
AEMO is currently investigating these LOR3 forecast conditions to confirm whether they are valid.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 27/06/2023
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 108747 is cancelled at 1000 hrs 26/06/2023.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 27/06/2023
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 108740 has been updated at 0530 hrs to the following:
From 1800 hrs 27/06/2023 to 1930 hrs 27/06/2023.
The maximum load (other than interruptible loads) forecast to be interrupted is 43 MW at 1830 hrs.
.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0600 hrs on 27/06/2023.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 27/06/2023
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 1800 hrs 27/06/2023 to 1900 hrs 27/06/2023.
The maximum load (other than interruptible loads) forecast to be interrupted is 5 MW at 1830 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0600 hrs on 27/06/2023.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 27/06/2023
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 108727 is cancelled at 0800 hrs 25/06/2023.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 27/06/2023
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 1800 hrs 27/06/2023 to 2000 hrs 27/06/2023.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 1830 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0600 hrs on 27/06/2023.
Manager NEM Real Time Operations
Declaration of electricity market resumption
Declaration of electricity market resumption
Refer initial AEMO Electricity Market Notice 107545
AEMO declares that the suspension of the spot market in Victoria will end at 1700 hrs on 23 April 2023.
The TNSP has taken sufficient steps to exclude the original event having influence on market processes and AEMO assesses that the possibility of suspending the spot market within the next 24 hours due to the same cause is minimal. AEMO also determines that it can operate the market in accordance with the provisions of the NER.
Relevant Market Notices issued under this suspension:
107545 and 107550
Manager NEM Real Time Operations