PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 14/06/2022
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 0700 hrs to 0730 hrs 14/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 171 MW at 0700 hrs.
[2.] From 1730 hrs to 2030 hrs 14/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 653 MW at 1900 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 13/06/2022
The Forecast LOR3 condition in the QLD region advised in AEMO Electricity Market Notice No. 97046 has been updated at 1130 hrs to the following:
[1.] From 1700 hrs 13/06/2022 to 2300 hrs 13/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1454 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1230 hrs on 13/06/2022
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 13/06/2022
The Forecast LOR3 condition in the QLD region advised in AEMO Electricity Market Notice No. 97035 has been updated at 0911 hrs to the following:
[1.] From 1700 hrs 13/06/2022 to 2030 hrs 13/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 513 MW at 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which they would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 13/06/2022
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1730 hrs 13/06/2022 to 1900 hrs 13/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 173 MW at approximately 1730 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 12/05/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 96233 is cancelled at 1700 hrs on 10/05/2022
No LOR3 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 12/05/2022
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0800 hrs 12/05/2022 to 1000 hrs 12/05/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 166 MW at 0830 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene is 0500 hrs on 12/05/2022.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 12/05/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 96225 is cancelled at 0800 hrs on 10/05/2022
No LOR3 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 12/05/2022
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 0830 hrs 12/05/2022 to 0900 hrs 12/05/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1 MW at 0830 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 12/05/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 96158 is cancelled at 1530 hrs on 08/05/2022
[No LOR3 condition is currently forecast in the STPASA period.]
Manager NEM Real Time Operations