STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/06/2022
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0700 hrs 17/06/2022 to 0900 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 0700 hrs.
2. From 1730 hrs 17/06/2022 to 1900 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 1730 hrs.
3. From 1930 hrs 17/06/2022 to 2300 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 1930 hrs.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 16/06/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 97982 has been updated at 1000 hrs to the following:
[1.] From 1730 hrs 16/06/2022 to 1900 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 218 MW at 1800 hrs.
[2.] From 2000 hrs 16/06/2022 to 2230 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 422 MW at 2030 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 16/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region on 16/06/2022
The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 97977 has been updated at 0930 hrs to the following:
[1.] From 1800 hrs 16/06/2022 to 1830 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 80 MW at 1800 hrs.
[2.] From 2000 hrs 16/06/2022 to 2200 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 418 MW at 2030 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1730 hrs on 16/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/06/2022
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 97972 has been updated at 0930 hrs to the following:
[1.] From 1800 hrs 16/06/2022 to 1830 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 80 MW at 1800 hrs.
[2.] From 2000 hrs 16/06/2022 to 2200 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 957 MW at 2100 hrs
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1730 hrs on 16/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 16/06/2022
The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 97829 has been updated at 0900 hrs to the following:
From 2030 hrs 16/06/2022 to 2130 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 231 MW at 2030 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 2000 hrs on 16/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region on 16/06/2022
The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 97853 has been updated at 0830 hrs to the following:
[1.] From 1730 hrs 16/06/2022 to 1900 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 506 MW at 1800 hrs.
[2.] From 2000 hrs 16/06/2022 to 2230 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 783 MW at 2100 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 16/06/2022.
AEMO Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/06/2022
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 97930 has been updated at 0830 hrs to the following:
[1.] From 1730 hrs 16/06/2022 to 1900 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 506 MW at 1800 hrs.
[2.] From 2000 hrs 16/06/2022 to 2230 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 820 MW at 2030 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 16/06/2022.
AEMO Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 16/06/2022
The Forecast LOR3 condition in the QLD region advised in AEMO Electricity Market Notice No. 97927 is cancelled at 0230 hrs 16/06/2022..
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 16/06/2022
The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 97879 has been updated at 2030 hrs to the following:
[1.] From 0900 hrs 16/06/2022 to 0930 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 0900 hrs.
[2.] From 1000 hrs 16/06/2022 to 1100 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 983 MW at 1000 hrs.
[3.] From 1400 hrs 16/06/2022 to 0400 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 3982 MW at 2000 hrs.
AEMO is seeking a market response.
AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0830 hrs on 16/06/2022.
AEMO Operations