Market Notices

98110RESERVE NOTICE16/06/2022 02:48:03 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98030 has been updated at 1400 hrs to the following:

[1.] From 0700 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 837 MW at 0730 hrs.

[2.] From 0900 hrs 17/06/2022 to 1200 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1410 MW at 1000 hrs.

[3.] From 1330 hrs 17/06/2022 to 0230 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 3310 MW at 2000 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0630 hrs on 17/06/2022.

AEMO Operations
98030RESERVE NOTICE16/06/2022 01:48:22 PM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0700 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 968 MW at 0730 hrs.

[2.] From 0900 hrs 17/06/2022 to 1200 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1319 MW at 1030 hrs

[3.] From 1400 hrs 17/06/2022 to 0230 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 3874 MW at 2030 hrs

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0630 hrs on 17/06/2022.

AEMO Operations
98022RESERVE NOTICE16/06/2022 12:09:32 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region on 16/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 98006 is cancelled at 1130 hrs 16/06/2022.

AEMO Operations
98019RESERVE NOTICE16/06/2022 11:58:11 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 16/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 97999 is cancelled at 1130 hrs 16/06/2022.

AEMO Operations
98014RESERVE NOTICE16/06/2022 11:50:06 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 16/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 97993 is cancelled at 1100 hrs 16/06/2022

AEMO Operations
98006RESERVE NOTICE16/06/2022 11:03:32 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region beginning on 16/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 97988 has been updated at 1030 hrs to the following:

[1.] From 1730 hrs 16/06/2022 to 1900 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 230 MW at 1800 hrs.

[2.] From 2000 hrs 16/06/2022 to 2230 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 424 MW at 2030 hrs.

[3.] From 0000 hrs 17/06/2022 to 0030 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 6 MW at 0000 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 16/06/2022.

AEMO Operations
98005RESERVE NOTICE16/06/2022 11:08:31 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0700 hrs to 1000 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 127 MW at 0800 hrs.

2. From 1730 hrs to 2030 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 65 MW at 1800 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
98000RESERVE NOTICE16/06/2022 11:05:51 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:

1. From 0730 hrs to 1000 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 0730 hrs.

2. From 1730 hrs to 1900 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 1730 hrs.

3. From 1930 hrs to 2100 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 1930 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
97999RESERVE NOTICE16/06/2022 10:53:34 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 16/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 97985 has been updated at 1030 hrs to the following:

[1.] From 1730 hrs 16/06/2022 to 1900 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 230 MW at 1800 hrs.

[2.] From 2000 hrs 16/06/2022 to 2230 hrs 16/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1123 MW at 2100 hrs.

[3.] From 0000 hrs 17/06/2022 to 0030 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 6 MW at 0000 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 16/06/2022.

AEMO Operations
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm