98264RESERVE NOTICE17/06/2022 09:39:53 AM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region beginning on 18/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following period:

[1.] From 0230 hrs 18/06/2022 to 0300 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 0 MW at 0230 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0200 hrs on 18/06/2022.

AEMO Operations
98257RESERVE NOTICE17/06/2022 05:39:04 AM

PDPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 2130 hrs 17/06/2022 to 2230 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 158 MW at 2130 hrs.

[2.] From 0230 hrs 18/06/2022 to 0400 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 431 MW at 0230 hrs.

AEMO is seeking a market response.

[AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


Manager NEM Real Time Operations
98238RESERVE NOTICE16/06/2022 11:24:26 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98227 is cancelled at 2320hrs 16/06/2022.

AEMO Operations
98237RESERVE NOTICE16/06/2022 11:23:28 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98228 is cancelled at 2320hrs 16/06/2022.

AEMO Operations
98236RESERVE NOTICE16/06/2022 11:21:56 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 98229 is cancelled at 2320hrs 16/06/2022.

AEMO Operations
98229RESERVE NOTICE16/06/2022 06:58:18 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region beginning on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the VIC region advised in AEMO Electricity Market Notice No. 98225 has been updated at 1830 hrs to the following:

[1.] From 0730 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 128 MW at 0730 hrs.

[2.] From 0900 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 17 MW at 0900 hrs.

[3.] From 1600 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 435 MW at 1600 hrs.

[4.] From 1700 hrs 17/06/2022 to 0100 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1433 MW at 2000 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.

AEMO Operations
98228RESERVE NOTICE16/06/2022 06:59:07 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98226 has been updated at 1830 hrs to the following:

[1.] From 0730 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 128 MW at 0730 hrs.

[2.] From 0900 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 17 MW at 0900 hrs.

[3.] From 1600 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 435 MW at 1600 hrs.

[4.] From 1700 hrs 17/06/2022 to 0230 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 3007 MW at 2000 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.

AEMO Operations
98227RESERVE NOTICE16/06/2022 06:57:19 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98223 has been updated at 1830 hrs to the following:

[1.] From 0730 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 128 MW at 0730 hrs.

[2.] From 0900 hrs 17/06/2022 to 0930 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 17 MW at 0900 hrs.

[3.] From 1700 hrs 17/06/2022 to 2100 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 273 MW at 1800 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.

AEMO Operations
98226RESERVE NOTICE16/06/2022 06:33:56 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 17/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98221 has been updated at 1800 hrs to the following:

[1.] From 0730 hrs 17/06/2022 to 0830 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 233 MW at 0730 hrs.

[2.] From 1530 hrs 17/06/2022 to 1630 hrs 17/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 428 MW at 1600 hrs.

[3.] From 1700 hrs 17/06/2022 to 0230 hrs 18/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 2995 MW at 2000 hrs.

AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0700 hrs on 17/06/2022.

AEMO Operations
X