Market Notices

98736RESERVE NOTICE21/06/2022 02:05:07 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the Vic Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the Vic region advised in AEMO Electricity Market Notice No. 98726 has been updated at 1330 hrs to the following:

[1.] From 0900 hrs 22/06/2022 to 0930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 63 MW at 0900 hrs.

[2.] From 1700 hrs 22/06/2022 to 1930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 903 MW at 1730 hrs.

[3.] From 2000 hrs 22/06/2022 to 2200 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1003 MW at 2000 hrs.


AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0830 hrs on 22/06/2022.

AEMO Operations
98735RESERVE NOTICE21/06/2022 02:03:42 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the QLD region advised in AEMO Electricity Market Notice No. 98725 has been updated at 1330 hrs to the following:

[1.] From 1730 hrs 22/06/2022 to 1930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 411 MW at 1800 hrs.

[2.] From 2000 hrs 22/06/2022 to 2200 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 412 MW at 2000 hrs.


AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 22/06/2022.

AEMO Operations
98733RESERVE NOTICE21/06/2022 02:02:08 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98724 has been updated at 1330 hrs to the following:

[1.] From 0900 hrs 22/06/2022 to 0930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 63 MW at 0900 hrs.

[2.] From 1730 hrs 22/06/2022 to 1930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 411 MW at 1800 hrs.

[3.] From 2000 hrs 22/06/2022 to 2200 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1003 MW at 2000 hrs.

[4.] From 0130 hrs 23/06/2022 to 0230 hrs 23/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 196 MW at 0130 hrs.


AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0830 hrs on 22/06/2022.

AEMO Operations
98732RESERVE NOTICE21/06/2022 02:00:46 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98727 has been updated at 1330 hrs to the following:

[1.] From 0830 hrs 22/06/2022 to 0930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 63 MW at 0900 hrs.

[2.] From 1700 hrs 22/06/2022 to 2200 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1104 MW at 2000 hrs.


AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0800 hrs on 22/06/2022.

AEMO Operations
98727RESERVE NOTICE21/06/2022 01:06:16 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 98712 has been updated at 1230 hrs to the following:

[1.] From 0830 hrs 22/06/2022 to 0930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 239 MW at 0900 hrs.

[2.] From 1000 hrs 22/06/2022 to 1030 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 67 MW at 1000 hrs.

[3.] From 1600 hrs 22/06/2022 to 2230 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1384 MW at 1830 hrs.



AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0800 hrs on 22/06/2022.

AEMO Operations
98726RESERVE NOTICE21/06/2022 01:03:37 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the Vic Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the Vic region advised in AEMO Electricity Market Notice No. 98717 has been updated at 1230 hrs to the following:

[1.] From 0900 hrs 22/06/2022 to 0930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 239 MW at 0900 hrs.

[2.] From 1000 hrs 22/06/2022 to 1030 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 67 MW at 1000 hrs.

[3.] From 1600 hrs 22/06/2022 to 2230 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1792 MW at 1730 hrs.


AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0830 hrs on 22/06/2022.

AEMO Operations
98725RESERVE NOTICE21/06/2022 01:01:29 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the QLD Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the QLD region advised in AEMO Electricity Market Notice No. 98714 has been updated at 1230 hrs to the following:

[1.] From 1730 hrs 22/06/2022 to 2200 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 444 MW at 1730 hrs.



AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 1700 hrs on 22/06/2022.

AEMO Operations
98724RESERVE NOTICE21/06/2022 01:00:09 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 3 (LOR3) in the NSW Region beginning on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the NSW region advised in AEMO Electricity Market Notice No. 98715 has been updated at 1230 hrs to the following:

[1.] From 0900 hrs 22/06/2022 to 0930 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 239 MW at 0900 hrs.

[2.] From 1000 hrs 22/06/2022 to 1030 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 67 MW at 1000 hrs.

[3.] From 1730 hrs 22/06/2022 to 2230 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 1890 MW at 2000 hrs.

[4.] From 2300 hrs 22/06/2022 to 2330 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 2300 hrs.

[5.] From 0100 hrs 23/06/2022 to 0230 hrs 23/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 437 MW at 0130 hrs.



AEMO is seeking a market response.

AEMO estimates the latest time it would need to intervene through an AEMO intervention event is 0830 hrs on 22/06/2022.

AEMO Operations
98717RESERVE NOTICE21/06/2022 11:36:29 AM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the VIC Region on 22/06/2022

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following periods:

1. From 0600 hrs to 1230 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 491 MW at 0800 hrs.

2. From 1300 hrs to 2330 hrs 22/06/2022.
The maximum load (other than interruptible loads) forecast to be interrupted is 557 MW at 1800 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations