Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region- 10-02-2017
Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region- 10-02-2017
An Actual LOR1 condition has been declared for the NSW Region from 1250 hrs.
The Actual LOR1 condition is forecast to exist until 2000 hrs
The contingency capacity reserve required is 1345 MW
The minimum LOR1 reserve available is 861 MW
Manager NEM Real Time Operations
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Refer to AEMO Electricity Market Notice 57339
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1600 hrs to 1700 hrs
The minimum reserve available is -77
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the South Australia region.
Cancellation of Actual (LOR1) condition in the South Australia region.
Refer to AEMO Electricity Market Notice No. 57349
The Actual LOR1 Condition in the South Australia Region is cancelled at 2000 hrs Thursday, 9 February 2017.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region. PD PASA.
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region.
An Actual LOR1 condition has been declared for the South Australia Region.
From 1900 hrs to 2000 hrs Thursday, 9 February 2017
The contingency capacity reserve required is 253 MW
The minimum reserve available is 200 MW
Manager NEM Real Time Operations
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1500 hrs to 1730 hrs
The minimum reserve available is --419 MW.
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region- 9/02/17
Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region- 9/02/17
An Actual LOR1 condition has been declared for the South Australia Region from 1430 hrs.
The Actual LOR1 condition is forecast to exist until 1530 hrs.
The contingency capacity reserve required is 414 MW
The minimum reserve available is 293 MW
Manager NEM Real Time Operations
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
Update - FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- PD PASA.
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1500 hrs to 1700 hrs
The minimum reserve available is --264 MW.
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- ST PASA.
FORECAST LACK OF RESERVE LEVEL 3 (LOR3) in the New South Wales region- ST PASA.
AEMO declares forecast LOR3 condition for the NSW Region for the following period.
Friday 10th February 2017 from 1600 hrs to 1630 hrs
The minimum reserve available is -19 MW.
This calculation is based on a LOR3 trigger level of 0 MW.
AEMO is seeking a market response.
AEMO will determine the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the South Australia region.
Cancellation of Actual (LOR1) condition in the South Australia region.
Refer to AEMO Electricity Market Notice No. 57287
The Actual LOR1 Condition in the South Australia Region is cancelled at 2100 hrs Wednesday, 8 February 2017.