57821RESERVE NOTICE03/03/2017 06:36:31 PM

Cancellation of Actual (LOR1) condition in the South Australia region - 03/03/2017

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the South Australia region - 03/03/2017

The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice No. 57820 is cancelled at 1835 hrs 03/03/2017

Manager NEM Real Time Operations
57820RESERVE NOTICE03/03/2017 05:52:07 PM

Cancellation of Actual (LOR2) condition in the South Australia region - 03/03/2017

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the South Australia region - 03/03/2017

The Actual LOR2 Condition in the South Australia Region advised in AEMO Electricity Market Notice No. 57818 & 57819 is cancelled at 1730 hrs 03/03/2017

An Actual LOR1 condition exists and is forecast to exist until 1830 hrs.
The contingency capacity reserve required is 450 MW
The minimum reserve available is 281 MW
AEMO is seeking a market response.

Manager NEM Real Time Operations
57779RESERVE NOTICE01/03/2017 06:54:52 PM

Cancellation of Actual (LOR1) condition in the South Australia region - 01/03/2017

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the South Australia region - 01/03/2017

The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice No. 57769 is cancelled at 1825 hrs 01/03/2017

Manager NEM Real Time Operations


57769RESERVE NOTICE01/03/2017 03:35:50 PM

Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region.- 01/03/17

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region.- 01/03/17
An Actual LOR1 condition has been declared for the South Australia Region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The contingency capacity reserve required is 570 MW
The minimum reserve available is 456 MW

Manager NEM Real Time Operations
57753RESERVE NOTICE28/02/2017 07:12:07 PM

Cancellation of Actual (LOR1) condition in the South Australia region.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the South Australia region.

Refer to AEMO Electricity Market Notice No. 57752

The Actual LOR1 Condition in the South Australia Region advised in AEMO Electricity Market Notice No. 57752 is cancelled at 1900 hrs Tuesday, 28 February 2017.


Manager NEM Real Time Operations

57752RESERVE NOTICE28/02/2017 03:34:50 PM

Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region.- 28/02/17

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the South Australia Region.- 28/02/17
An Actual LOR1 condition has been declared for the South Australia Region from 1530 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The contingency capacity reserve required is 570 MW
The minimum reserve available is 412 MW

Manager NEM Real Time Operations
57475RESERVE NOTICE12/02/2017 08:26:19 PM

Cancellation Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17

AEMO ELECTRICITY MARKET NOTICE

Cancellation Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17

Refer Electricity Market Notice 57472

The Actual LOR1 condition declared for the Qld region is cancelled at 2020 hrs 12/02/2017


Manager NEM Real Time Operations
57472RESERVE NOTICE12/02/2017 04:16:07 PM

Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the Qld Region - 12/02/17

An Actual LOR1 condition has been declared for the Qld region from 1600 hrs.
The Actual LOR1 condition is forecast to exist until 1730 hrs
The contingency capacity reserve required is 1123 MW
The minimum reserve available is 978 MW

Manager NEM Real Time Operations
57434RESERVE NOTICE11/02/2017 06:39:51 PM

Cancellation - Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region - 11-02-2017

AEMO ELECTRICITY MARKET NOTICE

Cancellation - Actual Lack Of Reserve Level 1 (LOR1 in the NSW Region - 11-02-2017

Refer Electricity Market Notice 57412

The Actual LOR1 declared for the NSW region is cancelled from 1820 hrs.