Market Notices

116503RESERVE NOTICE07/05/2024 12:01:42 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116502 is cancelled at 1100 hrs 07/05/2024.

No LOR2 condition is currently forecast in the STPASA period.


AEMO Operations
     
116502RESERVE NOTICE07/05/2024 10:02:31 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:

From 1700 hrs to 1800 hrs 08/05/2024.
The forecast capacity reserve requirement is 1198 MW.
The minimum capacity reserve available is 973 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations

     
116448NON-CONFORMANCE03/05/2024 07:10:20 AM

NON-CONFORMANCE Region VIC1 Friday, 3 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 3 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS3
Duration: 03/05/2024 07:00 to 03/05/2024 07:10
Amount: -45 MW
Constraint: NC-V_YWPS3

Auto-generated on behalf of Manager NEM Real Time Operations
     
116447NON-CONFORMANCE03/05/2024 06:35:20 AM

NON-CONFORMANCE Region NSW1 Friday, 3 May 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Friday, 3 May 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: BW04
Duration: 03/05/2024 06:20 to 03/05/2024 06:35
Amount: -43 MW
Constraint: NC-N_BW04

Auto-generated on behalf of Manager NEM Real Time Operations
     
116375NON-CONFORMANCE29/04/2024 08:55:22 PM

NON-CONFORMANCE Region NSW1 Monday, 29 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 29 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 29/04/2024 20:50 to 29/04/2024 20:55
Amount: -18 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
116369NON-CONFORMANCE29/04/2024 01:05:16 PM

NON-CONFORMANCE Region VIC1 Monday, 29 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 29 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: JLB01
Duration: 29/04/2024 13:00 to 29/04/2024 13:05
Amount: 35 MW
Constraint: NC-V_JLB01

Auto-generated on behalf of Manager NEM Real Time Operations
     
116345NON-CONFORMANCE26/04/2024 10:45:22 PM

NON-CONFORMANCE Region VIC1 Friday, 26 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 26 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS3
Duration: 26/04/2024 22:40 to 26/04/2024 22:45
Amount: 17 MW
Constraint: NC-V_YWPS3

Auto-generated on behalf of Manager NEM Real Time Operations
     
116076NON-CONFORMANCE10/04/2024 02:55:14 PM

NON-CONFORMANCE Region QLD1 Wednesday, 10 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 10 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 10/04/2024 14:35 to 10/04/2024 14:55
Amount: 16 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     
116047NON-CONFORMANCE08/04/2024 03:05:14 PM

NON-CONFORMANCE Region QLD1 Monday, 8 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Monday, 8 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MPP_2
Duration: 08/04/2024 15:00 to 08/04/2024 15:05
Amount: -43 MW
Constraint: NC-Q_MPP_2

Auto-generated on behalf of Manager NEM Real Time Operations
     