96997RESERVE NOTICE12/06/2022 09:42:57 PM

Cancellation of Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 12/06/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 12/06/2022

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.96992 is cancelled at 2130 hrs 12/06/2022.

Manager NEM Real Time Operations
96992RESERVE NOTICE12/06/2022 08:50:32 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 12/06/2022


AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 12/06/2022

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 2030 hrs.

The Actual LOR2 condition is forecast to exist until 2130 hrs.

The forecast capacity reserve requirement is 487 MW.
The minimum capacity reserve available is 403 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
96927RESERVE NOTICE10/06/2022 07:11:48 PM

Cancellation of Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2022

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No.96921 is cancelled at 1900 hrs 10/06/2022.

Manager NEM Real Time Operations
96921RESERVE NOTICE10/06/2022 06:21:22 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 10/06/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 10/06/2022

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1800 hrs.

The Actual LOR2 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 524 MW.
The minimum capacity reserve available is 311 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
95169RESERVE NOTICE08/03/2022 07:32:53 PM

Cancellation of Actual (LOR2) in the QLD region - 08/03/2022

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) in the QLD region - 08/03/2022

The Actual LOR2 Condition in the QLD Region advised in AEMO Electricity Market Notice No. 95166 is cancelled at 1930 hrs 08/03/2022.

Manager NEM Real Time Operations
95166RESERVE NOTICE08/03/2022 05:43:22 PM

Actual Lack Of Reserve Level 2 (LOR2) in the QLD Region on 08/03/2022

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the QLD region - 08/03/2022

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.

The Actual LOR2 condition is forecast to exist until 1900 hrs.

The forecast capacity reserve requirement is 443 MW.
The minimum capacity reserve available is 314 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
94993MARKET SUSPENSION01/03/2022 06:43:18 PM

Declaration of electricity market resumption

AEMO ELECTRICITY MARKET NOTICE
Declaration of electricity market resumption

Refer initial AEMO Electricity Market Notice 94979

AEMO declares that the suspension of the spot market in Tasmania will end at 1915 hrs on 1 March 2022.


Relevant Market Notices issued under this suspension:
94979
Manager NEM Real Time Operations
94979MARKET SUSPENSION01/03/2022 12:39:12 PM

Declaration of electricity market suspension

AEMO ELECTRICITY MARKET NOTICE
Declaration of electricity market suspension
AEMO declares the spot market suspended in Tasmania with Market Suspension Schedule Pricing (refer NER clause 3.14.5(b)) from Trading Interval 1240 hrs on 1 March 2022 until further notice.
Dispatch prices for the first one or two dispatch intervals of this market suspension will be reviewed manually.
AEMO has determined that it has become impossible to operate the spot market in accordance with the provisions of the Rules due to Failure of SCADA systems.
Manager NEM Real Time Operation
94694MARKET SUSPENSION18/02/2022 03:38:41 PM

Declaration of electricity market resumption

AEMO ELECTRICITY MARKET NOTICE
Declaration of electricity market resumption

Refer initial AEMO Electricity Market Notice 94690

AEMO declares that the suspension of the spot market in South Australia will end at 1610 hrs on 18 February 2022.


Relevant Market Notices issued under this suspension:
94690
Manager NEM Real Time Operations