STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/01/2022
The Forecast LOR1 condition in the QLD Rregion advised in AEMO Electricity Market Notice No 94112 is cancelled at 1400 hrs 28/01/2022.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 01/02/2022
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 1800 hrs 01/02/2022 to 1900 hrs 01/02/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 682 MW.
[2.] From 1600 hrs 02/02/2022 to 1700 hrs 02/02/2022.
The forecast capacity reserve requirement is 837 MW.
The minimum capacity reserve available is 489 MW.
[3.] From 1930 hrs 02/02/2022 to 2000 hrs 02/02/2022.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 796 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 01/02/2022
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 1830 hrs 01/02/2022 to 1900 hrs 01/02/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 752 MW.
[2.] From 1630 hrs 02/02/2022 to 1930 hrs 02/02/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 507 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 01/02/2022
The Forecast LOR1 conditions in the QLD region advised in AEMO Electricity Market Notice No. 94048 have been updated at 1400 hrs 27/01/2022 to the following:
1. From 1730 hrs 01/02/2022 to 2000 hrs 01/02/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 492 MW.
2. From 1630 hrs 02/02/2022 to 1730 hrs 02/02/2022.
The forecast capacity reserve requirement is 877 MW.
The minimum capacity reserve available is 492 MW.
3. From 1930 hrs 02/02/2022 to 2000 hrs 02/02/2022.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 772 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/01/2022
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1900 hrs 31/01/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 829 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region beginning on 01/02/2022
AEMO ELECTRICITY MARKET NOTICE
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 1730 hrs 01/02/2022 to 1800 hrs 01/02/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 589 MW.
[2.] From 1900 hrs 01/02/2022 to 2100 hrs 01/02/2022.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 445 MW.
[3.] From 1630 hrs 02/02/2022 to 1700 hrs 02/02/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 654 MW.
[4.] From 1930 hrs 02/02/2022 to 2100 hrs 02/02/2022.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 561 MW.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/01/2022
The Forecast LOR1 condition in the QLD Region advised in AEMO Electricity Market Notice No 94015 is cancelled at 1400 hrs 25/01/2022.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 01/02/2022
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following periods:
[1.] From 1730 hrs to 1830 hrs 01/02/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 543 MW.
[2.] From 1900 hrs to 2000 hrs 01/02/2022.
The forecast capacity reserve requirement is 870 MW.
The minimum capacity reserve available is 504 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the QLD Region on 31/01/2022
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:
From 1830 hrs to 1930 hrs on 31/01/2022.
The forecast capacity reserve requirement is 878 MW.
The minimum capacity reserve available is 675 MW.
AEMO Operations