Market Notices

116437RESERVE NOTICE02/05/2024 03:27:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 09/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 0000 hrs to 0200 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1304 MW.


AEMO Operations
     
116436RESERVE NOTICE02/05/2024 03:29:37 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 0500 hrs to 0830 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1265 MW.

From 1530 hrs to 2359 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1252 MW.


AEMO Operations

     
116435RESERVE NOTICE02/05/2024 03:28:45 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

From 1700 hrs to 1800 hrs 07/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1355 MW.

AEMO Operations.
     
116433RESERVE NOTICE02/05/2024 01:49:57 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:

[1.] From 1700 hrs 02/05/2024 to 1830 hrs 02/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1390 MW.

Manager NEM Real Time Operations
     
116388MARKET SYSTEMS30/04/2024 03:22:30 PM

CHG0088824 | Production | NEM Reform IESS Retail MSATS 53.0 Release

Change Number: CHG0088824

Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal
Service/ Component: MSATS - Consumer Administration and Transfer Solution(CATS)

Change Title: NEM Reform IESS Retail MSATS 53.0 Release
Change Start Date & Time: 12/05/2024 09:00:00 AEST
Change End Date & Time: 12/05/2024 17:00:00 AEST
Outage Start Date & Time: 12/05/2024 10:00:00 AEST
Outage End Date & Time: 12/05/2024 14:00:00 AEST

Environment: Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
116379MARKET SYSTEMS30/04/2024 01:51:08 PM

CHG0089106 | Pre-Production | Pre-Prod eMDM May Maintenance Release

Change Number: CHG0089106

Notification issued to: Market Notice
Notification Type: Initial

Change Type: Normal

Service/ Component: MDM - Meter Data Management

Change Title: Pre-Prod eMDM May Maintenance Release
Change Start Date & Time: 02/05/2024 13:00:00 AEST
Change End Date & Time: 02/05/2024 21:00:00 AEST
Outage Start Date & Time: 02/05/2024 13:00:00 AEST
Outage End Date & Time: 02/05/2024 17:00:00 AEST

Environment: Pre-Production
Participant Impact and Requirements: Users will not be able to access MSATS during the outage period.

Meter data processing and RM reports will not be available during the outage period.

User Rights Management (URM) will continue to operate, however the administration screens will not be accessible.

MSATS B2B/B2M Transactions and B2B MSATS Screens will be unavailable during this outage

NMI Discovery will not be available during the outage period.

CDR and CDP will not be available during the outage period.

Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.

Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
     
116374MARKET SYSTEMS29/04/2024 03:35:35 PM

CHG0088931 | Completed | Production | Planned System Maintenance activity.

Change Number: CHG0088931

Notification issued to: Market Notice
Notification Type: Completed

Change Type: Normal

Service/Component: EMS NEM - Network Outage Scheduler (NOS)

Change Title: Planned System Maintenance activity.

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.

     
116367MARKET SYSTEMS29/04/2024 10:36:02 AM

CHG0089027 | Cancelled | Pre-Production | Pre-Prod eMDM May Maintenance Release

Change Number: CHG0089027

Notification issued to: Market Notice
Notification Type: Cancelled

Change Type: Normal

Service/ Component: MDM - Meter Data Management

Change Title: Pre-Prod eMDM May Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600

     
116329GENERAL NOTICE25/04/2024 11:56:40 AM

Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024

AEMO ELECTRICITY MARKET NOTICE

The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024

A credible contingency event during this planned outage could cause a large reduction in generation in TAS.

Refer AEMO Network Outage Schedule (NOS) for further details.

Manager NEM Real Time Operations
     