STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 09/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 0000 hrs to 0200 hrs 09/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1304 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 08/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 0500 hrs to 0830 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1265 MW.
From 1530 hrs to 2359 hrs 08/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1252 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region beginning on 07/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
From 1700 hrs to 1800 hrs 07/05/2024.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1355 MW.
AEMO Operations.
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 02/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1700 hrs 02/05/2024 to 1830 hrs 02/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1390 MW.
Manager NEM Real Time Operations
[EventId:202404301730_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 30 April 2024 17:30
Issued by Australian Energy Market Operator Ltd at 1730 hrs on 30 April 2024
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 April 2024.
Refer to market notice: 116390
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.
The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1730 hrs on 30 April 2024.
This is an AEMO autogenerated Market Notice.
[EventId:202404301630_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 30 April 2024 16:30
Issued by Australian Energy Market Operator Ltd at 1630 hrs on 30 April 2024
ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 30 April 2024.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.
The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1630 hrs on 30 April 2024.
This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024
Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024
At 0830 hrs 27/04/2024 there was a short notice outage of Dapto - Marulan No. 8 330 kV Line.
Constraint set(s) invoked: N-DTMN_8_15M
This constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024
Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024
At 0837 hrs 23/04/2024 there was an unplanned outage of Para No 1 SVC.
Constraint set(s) invoked: S-PA_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation -Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024
Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024
A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1700 hrs 22/04/2024.
The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1450 hrs 22/04/2024
Constraint set(s) revoked: N-LDTM_82_OPEN
Manager NEM Real Time Operations