Filter by category
Filter by Date
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:
[1.] From 1730 hrs 18/05/2024 to 1830 hrs 18/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1281 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/05/2024
The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116652 is cancelled at 1645 hrs 17/05/2024.
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 18/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
[1.] From 1730 hrs 18/05/2024 to 1800 hrs 18/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1429 MW.
Manager NEM Real Time Operations
CHG0089703 | Production | Planned System Maintenance activity.
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMS NEM - Network Outage Scheduler (NOS)
Change Title: Planned System Maintenance activity.
Change Start Date & Time: 22/05/2024 11:00:00 AEST
Change End Date & Time: 22/05/2024 11:30:00 AEST
Outage Start Date & Time: 22/05/2024 11:00:00 AEST
Outage End Date & Time: 22/05/2024 11:30:00 AEST
Environment: Production
Participant Impact and Requirements: Network Outage Schedular (NOS) will be out of service during the maintenance activity. Please log off from NOS website during the outage. Users will have to log back in once the outage is completed. Please contact your NOS admin or AEMO support hub if your NOS account has been locked out after this change.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any
planned/unplanned maintenance activities .
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/05/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
1. From 0530 hrs to 0600 hrs 20/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1421 MW.
2. From 1600 hrs to 2230 hrs 20/05/2024.
The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 807 MW.
AEMO Operations
Update - Network Augmentation Commissioned - QLD Region - 15/05/2024
Update - Network Augmentation Commissioned - QLD Region - 15/04/2024
Refer Market notice: 115974 and 116446
Guybal Munjan 275 kV Switching Station has been commissioned.
The former Ross - Chalumbin No. 857 and Ross - Chalumbin No. 858 275 kV lines have been replaced with the following lines:
H13 Ross - H93 Guybal Munjan No. 8916 275 kV line
H13 Ross - H93 Guybal Munjan No. 8917 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 857 275 kV line
H93 Guybal Munjan - H32 Chalumbin No. 858 275 kV line
Manager NEM Real Time Operations
[EventId:202405150700_review] Prices for interval 15-May-2024 07:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 0655 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 07:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150655_review] Prices for interval 15-May-2024 06:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 0650 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202405150650_review] Prices for interval 15-May-2024 06:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 0645 hrs on 15 May 2024
PRICES ARE SUBJECT TO REVIEW for trading interval 15-May-2024 06:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.