Market Notices

111397RESERVE NOTICE16/11/2023 04:51:42 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/11/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 16/11/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.

The Actual LOR1 condition is forecast to exist until 1800 hrs.

The forecast capacity reserve requirement is 1430 MW.
The minimum capacity reserve available is 1293 MW.


Manager NEM Real Time Operations
111362RESERVE NOTICE15/11/2023 05:39:05 PM

Cancellation of Actual (LOR1) condition in the QLD region - 15/11/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the QLD region - 15/11/2023

The Actual LOR1 Condition in the QLD Region advised in AEMO Electricity Market Notice No.111357 is cancelled at 1700 hrs 15/11/2023.

Manager NEM Real Time Operations
111357RESERVE NOTICE15/11/2023 05:02:53 PM

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 15/11/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 15/11/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1630 hrs.

The Actual LOR1 condition is forecast to exist until 1700 hrs.

The capacity reserve requirement is 776 MW
The minimum capacity reserve available is 723 MW

Manager NEM Real Time Operations
111295RESERVE NOTICE14/11/2023 07:05:24 PM

Cancellation of Actual (LOR1) condition in the NSW region - 14/11/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 14/11/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.111287 is cancelled at 1900 hrs 14/11/2023.

Manager NEM Real Time Operations
111287RESERVE NOTICE14/11/2023 05:07:19 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/11/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 14/11/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1630 hrs.

The Actual LOR1 condition is forecast to exist until 1700 hrs.

The forecast capacity reserve requirement is 1415 MW.
The minimum capacity reserve available is 1376 MW.

Manager NEM Real Time Operations
111156RESERVE NOTICE12/11/2023 07:25:20 PM

Cancellation of Actual (LOR1) condition in the NSW region - 12/11/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 12/11/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.111155 is cancelled at 1920 hrs 12/11/2023.

Manager NEM Real Time Operations
111155RESERVE NOTICE12/11/2023 06:00:23 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 12/11/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 12/11/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.

The Actual LOR1 condition is forecast to exist until 1830 hrs.

The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1357 MW.


Manager NEM Real Time Operations
110931RESERVE NOTICE08/11/2023 06:33:57 PM

Cancellation of Actual (LOR1) condition in the NSW region - 08/11/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 08/11/2023

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.110927 is cancelled at 1825 hrs 08/11/2023.

Manager NEM Real Time Operations
110927RESERVE NOTICE08/11/2023 05:54:14 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/11/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/11/2023

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is not forecast in Pre Dispatch

The capacity reserve requirement is 1558 MW
The minimum capacity reserve available is 1524 MW

Manager NEM Real Time Operations