Cancellation of Actual (LOR1) condition in the Qld region - 05/07/2022
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.100023 is cancelled at 1900 hrs 05/07/2022
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the NSW region - 05/07/2022
The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.100022 is cancelled at 1900 hrs 05/07/2022
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/07/2022
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 05/07/2022
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The forecast capacity reserve requirement is 1068 MW.
The minimum capacity reserve available is 696 MW.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the NSW Region on 05/07/2022
Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 05/07/2022
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.
The forecast capacity reserve requirement is 1370 MW.
The minimum capacity reserve available is 1149 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the Qld region - 05/07/2022
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.100010 is cancelled at 1530 hrs 05/07/2022
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/07/2022
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 05/07/2022
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 1430 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs.
The forecast capacity reserve requirement is 851 MW.
The minimum capacity reserve available is 471 MW.
Manager NEM Real Time Operations
Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/07/2022
Update - Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 05/07/2022
The Actual LOR1 condition in the QLD region advised in AEMO Electricity Market Notice No. 99969 has been updated at 1235 hrs to the following:
The Actual LOR1 condition is forecast to exist until 1700 hrs.
The forecast capacity reserve requirement is 700 MW.
The minimum capacity reserve available is 538 MW.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the Qld region - 05/07/2022
The Actual LOR1 Condition in the Qld Region advised in AEMO Electricity Market Notice No.99987 is cancelled at 1300 hrs 05/07/2022
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the QLD Region on 05/07/2022
Actual Lack Of Reserve Level 1 (LOR1) in the QLD region - 05/07/2022
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the QLD region from 0800 hrs.
The Actual LOR1 condition is forecast to exist until 1000 hrs.
The forecast capacity reserve requirement is 620 MW.
The minimum capacity reserve available is 516 MW.
Manager NEM Real Time Operations