Market Notices

116543INTER-REGIONAL TRANSFER08/05/2024 03:50:23 PM

Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Blyth West to Munno Para 275 kV line - SA region - 08/05/2024

At 1536 hrs 08/05/2024 there was an unplanned outage of Blyth West to Munno Para 275 kV line.

The following constraint set(s) invoked at 1545 hrs 08/05/2024
S-X_BGBW+BWMP

This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116525INTER-REGIONAL TRANSFER08/05/2024 12:11:09 PM

Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Tamworth No. 1 330 kV Bus - NSW region - 08/05/2024

A planned outage of Tamworth No. 1 330 kV Bus in the NSW region was scheduled from 1200 hrs 08/05/2024 to 1800 hrs 10/05/2024.

The outage has been cancelled at 1154 hrs 08/05/2024

Constraint set(s) revoked: N-TW_330_BUS1, N-LDTW_84

This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
T-V-MNSP1

Manager NEM Real Time Operations
     
116514RESERVE NOTICE07/05/2024 07:17:19 PM

Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116513 is cancelled at 1915 hrs 07/05/2024.

Manager NEM Real Time Operations
     
116513RESERVE NOTICE07/05/2024 05:46:36 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1366 MW

Manager NEM Real Time Operations
     
116507INTER-REGIONAL TRANSFER07/05/2024 02:31:38 PM

Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - DAPTO - MARULAN 8 330KV LINE - NSW region - 07/05/2024

A planned outage of DAPTO - MARULAN 8 330KV LINE in the NSW region was scheduled from 0830 hrs 27/04/2024 to 1000 hrs 07/05/2024.

The outage has been rescheduled to be completed by 1200 hrs 08/05/2024.

Constraint set(s) invoked: N-DTMN_8_15M

This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1,VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116444RESERVE NOTICE02/05/2024 06:33:45 PM

Cancellation of Actual (LOR1) condition in the NSW region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 02/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116443 is cancelled at 1830 hrs 02/05/2024.

Manager NEM Real Time Operations
     
116443RESERVE NOTICE02/05/2024 05:52:09 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

The actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116440 has been updated at 1745 hrs 02/05/2024 to the following:

The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1146 MW

Manager NEM Real Time Operations
     
116440RESERVE NOTICE02/05/2024 05:16:09 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 888 MW

Manager NEM Real Time Operations
     
116346INTER-REGIONAL TRANSFER27/04/2024 08:41:29 AM

Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024

At 0830 hrs 27/04/2024 there was a short notice outage of Dapto - Marulan No. 8 330 kV Line.

Constraint set(s) invoked: N-DTMN_8_15M

This constraint set contains equations with the following interconnectors on the LHS.

N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm