Market Notices

116550ADMINISTERED PRICE CAP08/05/2024 07:45:12 PM

[EventId:197] AP STARTED for ENERGY in NSW1 at 08 May 2024 19:45

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1945 hrs on 08 May 2024

ADMINISTERED PRICE PERIOD DECLARED in NSW1 region.

AEMO has determined that the rolling sum of the uncapped spot prices for the NSW1 region over the previous 2016 trading intervals has exceeded the cumulative price threshold (CPT) of $1,490,200.00.

In accordance with Clause 3.14.2(b) of the National Electricity Rules, AEMO has determined that an administered price period will commence at the trading interval starting 1955 hrs on 08 May 2024 and will continue through to the end of that trading day.

An administered price cap (APC) of 600 $/MWh will apply to all trading intervals during this administered price period. This APC will apply to spot prices and to all market ancillary service prices in the NSW1 region.

An administered floor price (AFP) of -600 $/MWh will apply to spot prices.

AEMO will continue to monitor the rolling sum of the uncapped spot prices and issue further Market Notices as required.

This is an AEMO autogenerated Market Notice.
     
116548RESERVE NOTICE08/05/2024 07:11:28 PM

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 08/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No.116547 is cancelled at 1915 hrs 08/05/2024.

Manager NEM Real Time Operations
     
116547RESERVE NOTICE08/05/2024 05:45:01 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 08/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1830 hrs.

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1417 MW

Manager NEM Real Time Operations
     
116514RESERVE NOTICE07/05/2024 07:17:19 PM

Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 07/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116513 is cancelled at 1915 hrs 07/05/2024.

Manager NEM Real Time Operations
     
116513RESERVE NOTICE07/05/2024 05:46:36 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 07/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1730 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1450 MW
The minimum capacity reserve available is 1366 MW

Manager NEM Real Time Operations
     
116444RESERVE NOTICE02/05/2024 06:33:45 PM

Cancellation of Actual (LOR1) condition in the NSW region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the NSW region - 02/05/2024

The Actual LOR1 Condition in the NSW Region advised in AEMO Electricity Market Notice No. 116443 is cancelled at 1830 hrs 02/05/2024.

Manager NEM Real Time Operations
     
116443RESERVE NOTICE02/05/2024 05:52:09 PM

Update - Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

The actual LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116440 has been updated at 1745 hrs 02/05/2024 to the following:

The Actual LOR1 condition is forecast to exist until 1830 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 1146 MW

Manager NEM Real Time Operations
     
116440RESERVE NOTICE02/05/2024 05:16:09 PM

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 1 (LOR1) in the NSW region - 02/05/2024

An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 1700 hrs.
The Actual LOR1 condition is forecast to exist until 1900 hrs

The capacity reserve requirement is 1400 MW
The minimum capacity reserve available is 888 MW

Manager NEM Real Time Operations
     
115594RESERVE NOTICE11/03/2024 07:52:57 PM

Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024

The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.115593 is cancelled at 1945 hrs 11/03/2024.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm