Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control
Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Sunday, 15 May 2016
The Greenbank to Middle Ridge (8848) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0110 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations
NON-CONFORMANCE Region VIC1 Saturday, 14 May 2016
NON-CONFORMANCE VIC1 Region Saturday, 14 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: YWPS1
Duration: 14/05/2016 22:50 to 14/05/2016 22:55
Amount: -57 MW
Constraint: NC-V_YWPS1
Manager NEM Real Time Operations
Cancellation - Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Cancellation - Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Refer to MN 53189
The Greenbank to Middle Ridge (8848) 275kV Line was returned to service.
The following constraint set was revoked at 0650 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Refer to AEMO Network Outage Schedule for further details.
Manager NEM Real Time Operations
NON-CONFORMANCE Region TAS1 Saturday, 14 May 2016
NON-CONFORMANCE TAS1 Region Saturday, 14 May 2016
AEMO declared a schedule generating unit non-conforming
Unit: TREVALLN
Duration: 14/05/2016 07:50 to 14/05/2016 08:10
Amount: -12 MW
Constraint: NC-T_TREVALLN
Auto-generated on behalf of Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Refer MN 53191
The Tarong to South Pine (832) 275kV Line has been returned to service.
The following constraint set was revoked at 0550 hrs..
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Correction -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Correction -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Refer MN 53190
The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0200 hrs until further notice.
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Friday, 13 May 2016
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Friday, 13 May 2016
The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0200 hrs until further notice.
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
The Greenbank to Middle Ridge (8848) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0105 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Refer to AEMO Network Outage Schedule for further details.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation Blackwall SVC (QLD) - Friday, 13 May 2016
Inter-Regional Transfer limit variation Blackwall SVC (QLD) - Friday, 13 May 2016
At 1935 hrs there was an unplanned outage of the Blackwall No1 275 kV SVC in the Queensland region.
Constraint set Q-BK_SVC_BYPASS_B invoked from 1940 hrs until further notice.
This constraint set contains equations with the following interconnectors on the LHS.
NSW1-QLD1
N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations