Market Notices

116706PRICES SUBJECT TO REVIEW19/05/2024 03:25:24 PM

[EventId:202405191530_review] Prices for interval 19-May-2024 15:30 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1525 hrs on 19 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:30.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116705PRICES SUBJECT TO REVIEW19/05/2024 03:20:20 PM

[EventId:202405191525_review] Prices for interval 19-May-2024 15:25 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1520 hrs on 19 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:25.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116704PRICES SUBJECT TO REVIEW19/05/2024 03:15:27 PM

[EventId:202405191520_review] Prices for interval 19-May-2024 15:20 are subject to review

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1515 hrs on 19 May 2024

PRICES ARE SUBJECT TO REVIEW for trading interval 19-May-2024 15:20.

AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs


This is an AEMO autogenerated Market Notice.
     
116701RESERVE NOTICE19/05/2024 02:38:49 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116695 has been updated at 1430 hrs 19/05/2024 to the following:

[1.] From 1630 hrs 21/05/2024 to 2100 hrs 21/05/2024.
The forecast capacity reserve requirement is 1251 MW.
The minimum capacity reserve available is 1177 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
116698RESERVE NOTICE19/05/2024 11:31:33 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 22/05/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:

[1.] From 0600 hrs 22/05/2024 to 0730 hrs 22/05/2024.
The forecast capacity reserve requirement is 1354 MW.
The minimum capacity reserve available is 1334 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
116697RESERVE NOTICE19/05/2024 09:46:24 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116694 has been updated at 0945 hrs 19/05/2024 to the following:

[1.] From 1730 hrs 20/05/2024 to 1800 hrs 20/05/2024.
The forecast capacity reserve requirement is 1204 MW.
The minimum capacity reserve available is 1014 MW.


AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
116695RESERVE NOTICE19/05/2024 07:34:31 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116693 has been updated at 0730 hrs 19/05/2024 to the following:

[1.] From 0630 hrs 21/05/2024 to 0730 hrs 21/05/2024.
The forecast capacity reserve requirement is 1228 MW.
The minimum capacity reserve available is 1195 MW.

[2.] From 1630 hrs 21/05/2024 to 2130 hrs 21/05/2024.
The forecast capacity reserve requirement is 1168 MW.
The minimum capacity reserve available is 999 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
116694RESERVE NOTICE19/05/2024 07:33:22 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116692 has been updated at 0730 hrs 19/05/2024 to the following:

[1.] From 1700 hrs 20/05/2024 to 2100 hrs 20/05/2024.
The forecast capacity reserve requirement is 1114 MW.
The minimum capacity reserve available is 900 MW.

[2.] From 2330 hrs 20/05/2024 to 0000 hrs 21/05/2024.
The forecast capacity reserve requirement is 1152 MW.
The minimum capacity reserve available is 1144 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
116693RESERVE NOTICE18/05/2024 11:32:18 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 116685 has been updated at 2330 hrs 18/05/2024 to the following:

[1.]From 1630 hrs 21/05/2024 to 2130 hrs 21/05/2024.
The forecast capacity reserve requirement is 1213 MW.
The minimum capacity reserve available is 999 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm