Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024
At 0600 hrs 15/03/2024 there was a short notice outage of Robertstown - Tungkillo No. 2 275 kV Line.
At 0615 hrs 15/03/2024 there was a short notice outage of Tungkillo - Para No. 1 275 kV Line.
In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.
CA_SYDS_5505DC4C from 06:00 hrs until further notice
These constraint sets contains equations with the following interconnector on the LHS;
V-S-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024
Inter-regional transfer limit variation - constraint automation to manage Power System Security in SA region - 15/03/2024
In order to maintain the power system in a secure operating state in the SA region, AEMO has invoked the following automated constraint sets.
CA_SYDS_5505D0BC from 04:40 hrs to 05:10 hrs
CA_SYDS_5505D516 from 04:55 hrs to 05:10 hrs
These constraint sets contains equations with the following interconnector on the LHS;
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024
Inter-regional transfer limit variation - Robertstown - Tungkillo No. 1 275 kV Line - SA region - 14/03/2024
At 2307 hrs 14/03/2024 there was an unplanned outage of Robertstown - Tungkillo No. 1 275 kV Line.
The following constraint set(s) invoked at 2315 hrs 14/03/2024
S-RBTU
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024
Inter-regional transfer limit variation - Lismore 132kV SVC - NSW region - 14/03/2024
At 0800 hrs 14/03/2024 there was a short notice outage of Lismore 132kV SVC.
The following constraint set(s) invoked at 0800 hrs 14/03/2024
N-LS_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
N-Q-MNSP1,NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024
Cancellation of Actual (LOR1) condition in the SA region - 11/03/2024
The Actual LOR1 Condition in the SA Region advised in AEMO Electricity Market Notice No.115593 is cancelled at 1945 hrs 11/03/2024.
Manager NEM Real Time Operations
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024
Actual Lack Of Reserve Level 1 (LOR1) in the SA region - 11/03/2024
An Actual LOR1 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1830 hrs.
The Actual LOR1 condition is forecast to exist until 2030 hrs
The capacity reserve requirement is 498 MW
The minimum capacity reserve available is 255 MW
Manager NEM Real Time Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:
[1.] From 1930 hrs 11/03/2024 to 2030 hrs 11/03/2024.
The forecast capacity reserve requirement is 469 MW.
The minimum capacity reserve available is 402 MW.
Manager NEM Real Time Operations
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115588 is cancelled at 0717 hrs 11/03/2024.
Manager NEM Real Time Operations
PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/03/2024
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 115587 has been updated at 0520 hrs to the following:
[1.] From 1930 hrs 11/03/2024 to 2000 hrs 11/03/2024.
The forecast capacity reserve requirement is 600 MW.
The minimum capacity reserve available is 545 MW.
Manager NEM Real Time Operations