Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8849) 275kV Line (Qld) - Voltage Control
Inter-regional transfer limit variation - Greenbank to Middle Ridge (8849) 275kV Line (Qld) - Voltage Control - Monday, 16 May 2016
The Greenbank to Middle Ridge (8849) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0015 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations
Cancellation - Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - 15 May 2016
Cancellation - Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - 15May 2016
Refer to MN 53248
The Greenbank to Middle Ridge (8848) 275kV Line was returned to service.
The following constraint set was revoked at 0800 hrs
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Refer to AEMO Network Outage Schedule for further details.
Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Sunday, 15 May 2016
Refer MN 53250
The Tarong to South Pine (832) 275kV Line has been returned to service.
The following constraint set was revoked at 0605 hrs..
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control
Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Sunday, 15 May 2016
The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0245 hrs until further notice.
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500kV Line (VIC) - Voltage Control
Inter-regional transfer limit variation: Hazelwood - South Morang No.1 500kV Line (VIC) - Voltage Control - Sunday, 15th May 2016
The Hazelwood - South Morang No.1 500kV Line has been de-energised to manage voltages in the VIC region.
The following constraint set was invoked at 0230 hrs
V-HWSM
The constraint set contains equations with the following interconnectors on the LHS.
NSW1-QLD1
T-V-MNSP1
V-S-MNSP1
V-SA
VIC1-NSW1
Refer to AEMO Network Outage Schedule for further details and return to service times
Manager NEM Real Time Operations
Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control
Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Sunday, 15 May 2016
The Greenbank to Middle Ridge (8848) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0110 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Manager NEM Real Time Operations
Cancellation - Inter-regional Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Cancellation - Inter-regional transfer limit variation - Greenbank to Middle Ridge (8848) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Refer to MN 53189
The Greenbank to Middle Ridge (8848) 275kV Line was returned to service.
The following constraint set was revoked at 0650 hrs until further notice.
Q-MRGB_8848_8849
The constraint set contains equations with the following interconnectors on the LHS.
NSW-QLD1
N-Q-MNSP1
Refer to AEMO Network Outage Schedule for further details.
Manager NEM Real Time Operations
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Cancellation -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Refer MN 53191
The Tarong to South Pine (832) 275kV Line has been returned to service.
The following constraint set was revoked at 0550 hrs..
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations
Correction -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Correction -Inter-regional transfer limit variation - Tarong to South Pine (832) 275kV Line (Qld) - Voltage Control - Saturday, 14 May 2016
Refer MN 53190
The Tarong to South Pine (832) 275kV Line has been de-energised to manage voltages in the Qld region.
The following constraint set was invoked at 0200 hrs until further notice.
Q-TRSP_832
The constraint set contains equations with the following interconnectors on the LHS.
N-Q-MNSP1
Manager NEM Real Time Operations