QNI Minor testing 16 August 2023
Refer to market notice 109044
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1200 MW on Wednesday 16th August from 0900 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
Cancellation - Psymetrix PhasorPoint - Unplanned Outage - 16/08/2023
Refer AEMO Electricity Market Notice 109331
AEMO Psymetrix PhasorPoint application has returned to service.
Constraint set I-OSC_STAB_MON revoked at 0205 hrs.
Manager NEM Real Time Operations
Psymetrix PhasorPoint - Unplanned Outage - 16/08/2023
Psymetrix PhasorPoint - Unplanned Outage - 16/08/2023
There is an unplanned outage of AEMO Psymetrix PhasorPoint application.
Constraint set I-OSC_STAB_MON invoked at 0140 hrs 16/08/2023.
This constraint sets contain equations with the following interconnectors on the LHS.
NSW1-QLD1
V-S-MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations
QNI Minor testing 26 July 2023
Refer to market notice 109017
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1250 MW on Wednesday 26th July from 1130 to 1400hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
Network Augmentation Commissioned - NSW Region - 22/07/2023
Network Augmentation Commissioned - NSW Region - 22/07/2023
The following reactive plant has been commissioned at Wagga 330kV substation at 1415 hrs 22/07/2023.
No 4 330 kV 100 MVAR Capacitor
Manager NEM Real Time Operations
QNI Minor testing 22-23 July 2023
Refer to market notice 108796
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1250 MW from Saturday 22nd July 0000hrs through to Sunday 23rd July at 2359hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Network Augmentation Commissioned - Vic Region - 13/07/2023
A network augmentation has been commissioned the Vic region at 1755 hrs 13/07/2023 as follows:
Commissioned: Glenrowan W1 220kV/33kV Transformer.
Manager NEM Real Time Operations
QNI Minor testing 1-2 July 2023
Refer to market notice 105482
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1200 MW from Saturday 1st July 0000hrs through to Sunday 2nd July at 2359hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
AEMO Operations
Network Augmentation Commissioned - QLD Region - 30/06/2023
Network Augmentation Commmissioned - QLD Region - 30/06/2023
The Ross 275/132 kV No. 8 Transformer has been commissioned at 1200 hrs 30/06/2023.
Manager NEM Real Time Operations