Basslink Availability
Basslink Availability
Basslink restored to full operation at 1151 hrs Monday, 13 June 2016
Manager NEM Real Time Operations
Changes to raise FCAS requirements in Tasmania
Changes to raise FCAS requirements in Tasmania
Refer to AEMO Electricity market notice 51618
The adaptive under-frequency load shedding scheme (AUFLS) was implemented in January 2016 to reduce the contingency raise FCAS requirements in Tasmania. TasNetworks has advised AEMO this scheme was disabled at 1000 hrs 8 June 2016. Tasmanian contingency FCAS requirements now do not use the reduction provided by this scheme.
Ben Blake
AEMO Operations
Constraint Automation to Manage Power Security in Vic Region.
Constraint Automation to Manage Power Security in Vic Region, Monday, 06 June 2016.
AEMO network analysis indicated that the trip of the Hazelwood Power station to Hazelwood Terminal station No.2 220 kV line would result in an overload of the Hazelwood Power station to Hazelwood Terminal station A1 500 / 220 kV transformer.
AEMO invoked automated constraint set CA_SPS_4667C455 from 1850 to 1905 hrs to manage power system security.
Manager NEM Real Time Operations
Planned outage of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 29 May 2016
This market notice is FOR INFORMATION ONLY.
There is short notice planned outage of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line between 0630-1600hrs on 29 May 2016 in Victoria region.
During this outage, following the next contingency (trip of the Moorabool-Sydenham No.2 500 kV line) South Australia region still remains connected to the NEM. However if this contingency occurs, AEMO will invoke the following FCAS regulation constraint sets to secure the power system in South Australia region:
F-S_LREG_0035
F-S_RREG_0035
Please also refer to market notice 52838.
Refer to AEMO Network Outage Schedule (NOS) for further details
Operations Planning
Cancellation - Brisbane Communication Issues - 27th May 2016
Cancellation - Brisbane Communication Issues - 27th May 2016
Refer to MN 53535
This is to advise that the problems on the AEMO Brisbane Control Centre Phone system have been resolved.
Participants may noiw use normal Brisbane Control Centre and Sydney Control Centre contact numbers.
Manager NEM Real Time Operations
Brisbane Communication Issues - 27th May 2016
Brisbane Communication Issues - 27th May 2016
This is to advise that problems exist on the AEMO Brisbane Control Centre Phone system.
Participants who normally communicate with the Brisbane Control Centre are advised to utilise the backup telephone numbers or the alternative Sydney Control Centre contact numbers.
Further information will be provided when the problem is rectified.
Manager NEM Real Time Operations
Planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 25 and 30 May 2016
Planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line - Victoria Region on 25 May and 30 May 2016.
There are planned outages of Moorabool-Sydenham No.1 500 kV line and Sydenham-South Morang No.1 500 kV line between 0630-1630hrs on 25 May 2016 and 0630-1800hrs on 30 May 2016.
During these outages, South Australia region remains connected to the NEM for the first contingency (trip of the Moorabool - Sydenham No.2 500 kV line). However, there is a potential risk of South Australia region separation from the rest of the NEM for the subsequent contingency following the first contingency.
AEMO will invoke the following FCAS regulation constraint sets after the first contingency during this outage to secure the power system in South Australia region.
F-S_LREG_0035
F-S_RREG_0035
Refer to AEMO Network Outage Schedule (NOS) for further details
Operations Planning
[EventId:201605191025_confirmed] Prices for interval 19-May-2016 10:25 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1709 hrs on 19 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 19-May-2016 10:25.
In accordance with Market Notice 53415 AEMO has reviewed this dispatch interval and determined that:
- Over-Constrained Dispatch has been resolved for this interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
TAS1 $13,800.00 $345.80
RAISE5MIN
TAS1 $13,800.00 $4.20
RAISE60SEC
TAS1 $13,800.00 $68.30
RAISE6SEC
TAS1 $13,800.00 $162.35
RAISEREG
TAS1 $13,800.00 $4.20
This is an AEMO autogenerated Market Notice.
[EventId:201605191020_confirmed] Prices for interval 19-May-2016 10:20 are now confirmed
Issued by Australian Energy Market Operator Ltd at 1708 hrs on 19 May 2016
PRICES ARE NOW CONFIRMED for dispatch interval 19-May-2016 10:20.
In accordance with Market Notice 53414 AEMO has reviewed this dispatch interval and determined that:
- Manifestly Incorrect Inputs did not apply
- Over-Constrained Dispatch has been resolved for dispatch interval
Changed Prices ($/MWh)
TYPE
Region Original Adjusted
Price Price
ENERGY
TAS1 $13,800.00 $317.78
LOWER6SEC
TAS1 $13,800.00 $0.12
RAISE5MIN
TAS1 $13,800.00 $4.20
RAISE60SEC
TAS1 $13,800.00 $0.80
RAISE6SEC
TAS1 $13,800.00 $311.97
RAISEREG
TAS1 $13,800.00 $4.20