54798GENERAL NOTICE29/08/2016 09:05:25 AM

Planned outage of Heywood to Mortlake PS 500kV line in Victoria region from 06/09/2016 0730 hrs to 06/09/2016 1630 hrs

AEMO ELECTRICITY MARKET NOTICE.

This market notice is FOR INFORMATION ONLY.

The Heywood to Mortlake PS 500kV line in Victoria Region is planned out of service from 0730 hrs on 06 September 2016 to 1630 hrs on 06 September 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-HYMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-X_BC_CP
V-HYMO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.


Edmund Hon
AEMO Operations
54793GENERAL NOTICE27/08/2016 11:17:16 AM

Update - Lower Regulation FCAS Increased - 27/08/16

AEMO ELECTRICITY MARKET NOTICE

Update - Variation to FCAS regulation requirements: NEM Global for Mainland Regulation - 27/08/16.

Refer Market Notice 54792

FCAS Lower regulation requirements were increased to manage time error to within standards.

The following constraint was invoked to manage lower regulation requirements.

F-MAIN_LREG_0400 invoked from 0925 hrs to 1050 hrs

Manager NEM Real Time Operations
54792GENERAL NOTICE27/08/2016 09:42:52 AM

Lower Regulation FCAS Increased -27/08/16

AEMO ELECTRICITY MARKET NOTICE

Variation to FCAS regulation requirements: NEM Global for Mainland Regulation - 27/08/2016.

FCAS Lower regulation requirements were increased to manage time error to within standards.

The following constraint was invoked to manage lower regulation requirements.

F-MAIN_LREG_400 invoked from 0925 hrs.

Manager NEM Real Time Operations
54772GENERAL NOTICE23/08/2016 05:28:09 PM

Telstra planned - NSW RTNet Outage

AEMO ELECTRICITY MARKET NOTICE

Telstra have a planned outage which will affect NSW RTNET link.

The impacted circuit will be unavailable to process data for one15 minute outage during the below change window:


Start Date & Time: 24/08/2016 01:00:00
Finish Date & Time: 24/08/2016 06:00:00
Time Zone: AEST
Change Description: Maintenance work

If participants are experiencing difficulties contacting the AEMO control room, please use the back-up phone numbers previously advised


Manager NEM Real Time Operations


54736GENERAL NOTICE15/08/2016 07:45:09 AM

Planned outage of Moorabool to Mortlake PS 500kV line in Victoria region from 15/09/2016 0700 hrs to 15/09/2016 1700 hrs

AEMO ELECTRICITY MARKET NOTICE.

This market notice is FOR INFORMATION ONLY.

The Moorabool to Mortlake PS 500kV line in Victoria Region is planned out of service from 0700 hrs on 15 September 2016 to 1700 hrs on 15 September 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-MLMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLMO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Edmund Hon
AEMO Operations
54735GENERAL NOTICE15/08/2016 07:42:44 AM

Planned outage of Moorabool to Mortlake PS 500kV line in Victoria region from 14/09/2016 0700 hrs to 14/09/2016 1700 hrs

AEMO ELECTRICITY MARKET NOTICE.

This market notice is FOR INFORMATION ONLY.

The Moorabool to Mortlake PS 500kV line in Victoria Region is planned out of service from 0700 hrs on 14 September 2016 to 1700 hrs on 14 September 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-MLMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLMO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Edmund Hon
AEMO Operations
54734GENERAL NOTICE15/08/2016 07:39:40 AM

Planned outage of Moorabool to Mortlake PS 500kV line in Victoria region from 13/09/2016 0700 hrs to 13/09/2016 1700 hrs

AEMO ELECTRICITY MARKET NOTICE.

This market notice is FOR INFORMATION ONLY.

The Moorabool to Mortlake PS 500kV line in Victoria Region is planned out of service from 0700 hrs on 13 September 2016 to 1700 hrs on 13 September 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-MLMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLMO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.

Edmund Hon
AEMO Operations
54714GENERAL NOTICE12/08/2016 04:15:32 PM

Dispatch and reconciliation reporting issue with local FCAS regulation recovery

Dispatch and reconciliation reporting issue with local FCAS regulation recovery

Reports: DISPATCH_FCAS_REQ, PREDISPATCH_FCAS_REQ, and SET_FCAS_REGULATION_TRK

AEMO advises that DISPATCH_FCAS_REQ and PREDISPATCH_FCAS_REQ estimation reports and SET_FCAS_REGULATION_TRK reconciliation will not correctly account for Market Participants with generation in multiple NEM regions under different Participant IDs for local FCAS regulation requirements. This does not impact the calculation of settlement amounts, and only applies to requirements for local regulation FCAS.

AEMO estimates settlement amounts for each participant on a daily basis as part of routine prudential monitoring, and this information is distributed to each participant shortly after the end of the settlement day (ending midnight). These amounts are not impacted by the dispatch and reconciliation reporting issue.

AEMO is currently working on a fix to all three reports, and the fix will be in place by Friday 26 August 2016.

If you have questions relating to this matter please contact Chin Chan, Group Manager Market Management via 03 9609 8345.
54713GENERAL NOTICE12/08/2016 02:50:27 PM

Outage cancelled - Planned outage of Moorabool to Mortlake PS 500kV line in Victoria region from 28/08/2016 0630 hrs to 28/08/2016 1800 hrs

AEMO ELECTRICITY MARKET NOTICE.

** The outage have been cancelled by Ausnet **

This market notice is FOR INFORMATION ONLY.

The Moorabool to Mortlake PS 500kV line in Victoria Region is planned out of service from 0630 hrs on 28 August 2016 to 1800 hrs on 28 August 2016.

During this outage, a credible contingency can separate South Australia region from the rest of the NEM.

Under these circumstances, 35 MW of Raise and Lower regulation FCAS will be sourced from South Australia for the duration of this outage. In addition, consistent with AEMO existing procedures, adequate contingency FCAS lower requirements will also be sourced from South Australia at times when power transfer is from South Australia to Victoria.

The following constraint sets have been invoked for this outage:

F-V-MLMO (includes F-S_LREG_0035 and F-S_RREG_0035)
S-BOTH_BLKRG_C_OS
V-MLMO

Refer AEMO Network Outage Schedule (NOS) for further details.

AEMO will continue monitoring this proposed outage and will update the Market accordingly.