QNI Minor testing 26 August 2023
Refer to market notice 109333
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1200 MW on Saturday 26th August from 0630 to 0900hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
Network Augmentation Commissioned - Vic Region - 24/08/2023
Network augmentation change in the Vic region at 1603 hrs 24/08/2023 as follows:
Commissioned: Tarrone Terminal Station, K2 transformer 500 kV/132 kV.
Manager NEM Real Time Operations
Network Augmentation Decommissioned - QLD Region - 21/08/2023
Network augmentation has been decommissioned in the QLD region at 1355 hrs 21/08/2023 as follows:
Mudgeeraba No.3 275/110 kV transformer
Manager NEM Real Time Operations
Update Planned outage of Dumaresq - Bulli Creek (8L/8M) 330kV lines in the QLD-NSW region on 21/08/2023
Refer to AEMO Market Notice 109374.
The Dumaresq - Bulli Creek (8L/8M) 330 kV lines in the Queensland (QLD) and New South Wales (NSW) regions planned outage have now been rescheduled to the following periods:
- Dumaresq - Bulli Creek (8M) 330 kV line from 0800 - 1200 hrs on 21/08/2023
- Dumaresq - Bulli Creek (8L) 330 kV line from 1200 - 1600 hrs on 21/08/2023
These outages are considered High Impact Outages (HIO).
A credible contingency event during this planned outage could cause synchronous separation of the QLD region from the rest of the NEM.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
Planned outage of Dumaresq - Bulli Creek (8L/8M) 330kV lines in the QLD-NSW region on 20/08/2023
The Dumaresq - Bulli Creek (8L/8M) 330 kV lines in the Queensland (QLD) and New South Wales (NSW) regions are planned to be out of service during the following periods:
- Dumaresq - Bulli Creek (8M) 330 kV line from 0800 - 1200 hrs on 20/08/2023
- Dumaresq - Bulli Creek (8L) 330 kV line from 1200 - 1600 hrs on 20/08/2023
These outages are considered High Impact Outages (HIO).
A credible contingency event during this planned outage could cause synchronous separation of the QLD region from the rest of the NEM.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
QNI Minor testing 16 August 2023
Refer to market notice 109044
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1200 MW on Wednesday 16th August from 0900 to 1700hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake
Cancellation - Psymetrix PhasorPoint - Unplanned Outage - 16/08/2023
Refer AEMO Electricity Market Notice 109331
AEMO Psymetrix PhasorPoint application has returned to service.
Constraint set I-OSC_STAB_MON revoked at 0205 hrs.
Manager NEM Real Time Operations
Psymetrix PhasorPoint - Unplanned Outage - 16/08/2023
Psymetrix PhasorPoint - Unplanned Outage - 16/08/2023
There is an unplanned outage of AEMO Psymetrix PhasorPoint application.
Constraint set I-OSC_STAB_MON invoked at 0140 hrs 16/08/2023.
This constraint sets contain equations with the following interconnectors on the LHS.
NSW1-QLD1
V-S-MNSP1
V-SA
VIC1-NSW1
Manager NEM Real Time Operations
QNI Minor testing 26 July 2023
Refer to market notice 109017
There is an opportunity for testing QNI Minor for flows from Qld to NSW up to 1250 MW on Wednesday 26th July from 1130 to 1400hrs.
This test includes a trip and reclose of a line in northern NSW.
Please also refer to the published formal QNI minor testing information at the following link:
https://www.aemo.com.au/consultations/current-and-closed-consultations/qld-to-nsw-interconnector-qni-upgrade
Ben Blake