105936CONSTRAINTS17/02/2023 05:07:05 PM

Changes to Murraylink Very Fast Runback and constraints in Victoria

AEMO ELECTRICITY MARKET NOTICE

The Murraylink Very Fast Runback (VFRB) scheme is being modified to increase the capacity of the network due to the increase in generation in the area. The scheme will be changed so Murraylink VFRB can be activated / de-activated depending on the time of day on the monitored 220kV lines in north-west Victoria.

The changes to the scheme will be activated and constraint equaiton modified at 1200hrs Monday 20th February 2023. The following system normal constraint equations will be modified:
V^^V_NIL_KGTS
V^^V_NIL_KGTS_2
V>>SML_NIL_7A
V>>SML_NIL_7B
V>>SML_NIL_7C
V>>V_NIL_13
V>>V_NIL_14
V>>V_NIL_20
V>>V_NIL_21
V>>V_NIL_22
V>>V_NIL_23
V>>V_NIL_24
V>>V_NIL_25
V>>V_NIL_26
V>>V_NIL_26_1
V>>V_NIL_26A
V>>V_NIL_26A_1

For full details on the factors on constraint equations and all the constrint equation changes - these have now been loaded into AEMO's pre-production systems.

Ben Blake
AEMO Operations
102074CONSTRAINTS05/10/2022 01:28:35 PM

Update to system strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 101018

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Kaban wind farm in Far North Queensland, the system normal equations have been revised.

A revision to the constraint equations will be implemented at 1530 hrs on Wednesday 5th October 2022.

The new combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases.

The constraint equation in the Q-NIL set of the form below will be modified:

Q_NIL_STRGTH_XXXX
Q_NIL_STRGTH_XXXX_I


AEMO Operations
101368CONSTRAINTS26/08/2022 10:59:09 AM

New Victorian system normal voltage stability limit

AEMO ELECTRICITY MARKET NOTICE

AEMO has identified a new voltage collapse issue in south-west Victoria. The voltage collapse occurs in the south-west region for loss of the Haunted Gully to Moorabool 500 kV line with simultaneous trip of both APD potlines as per Market Notice 91405.

The limit will manage flow towards Moorabool on the cut-set of Haunted Gully to Moorabool and Mortlake to Moorabool 500 kV lines.

The new constraint equation includes generators in south-west Victoria on the left-hand side as well as Heywood interconnector. Full details on the limits advice are to be published on 30th August 2022 on the AEMO website: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

The following constraint equation will be implemented and added to constraint set V-NIL at 1000 hrs on Tuesday 30th August 2022:
V^^V_NIL_SWVIC

For full details on the factors this constraint equation has now been loaded into AEMO's pre-production systems.

For further details on this constraint equation please contact terry.liu@aemo.com.au

Terry Liu
AEMO Operations
101028CONSTRAINTS16/08/2022 11:57:21 AM

Update to Vic to NSW voltage collapse limit

AEMO ELECTRICITY MARKET NOTICE

Refer to Market Notice 82819

AEMO has completed a comprehensive review of the system normal voltage stability limit for loss of all APD potlines for flows from Victoria to New South Wales. The revised limit is the result of latest network configuration, comprehensive generation/load patterns, and recent commissioned generators in Victoria and southern NSW which could potentially mean higher transfers into NSW under some generation/load scenarios.

The revised constraint equation includes generators in southern NSW, north-west Victoria and hydro generation at Mt. Beauty on the left-hand side as well as VIC1-NSW1 and Murraylink. Full details on the limits advice are to be published on 18/08/2022 on the AEMO website: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

The constraint is most likely to bind when there is low Vic demands and high transfers to NSW. When it binds it will restrict Vic to NSW transfers and southern NSW units.

This revised limit will be implemented to the following constraint equation at 1000 hrs Thursday 18th August 2022.
V^^N_NIL_1

For further details on this constraint equation please contact terry.liu@aemo.com.au


Terry Liu
AEMO Operations
101018CONSTRAINTS16/08/2022 09:23:02 AM

Update to System strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 93841

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to reduced numbers of Gladstone units online, the system normal equations have been revised to include below combination.

-If Stanwell >=2, Stanwell + Calllide >=3, Gladstone >= 1, Stanwell + Callide + Gladstone >= 7, Kareeya >=2, Haughton Syncon status = ON, North Queensland load >=250 MW,
Ross+FNQ load >=100 MW, limit Mt Emerald Windfarm to 80% and no limit to other solar farms.

A revision to the constraint equations will be implemented at 1100 hrs on Tuesday 16th August 2022.

The new combinations will be published in a limits advice document on AEMO's website on Wednesday 17th August 2022.
For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases.

The constraint equations in the Q-NIL set of the form below will be modified:

Q_NIL_STRGTH_CLRSF
Q_NIL_STRGTH_COLSF
Q_NIL_STRGTH_DAYSF
Q_NIL_STRGTH_HAMSF
Q_NIL_STRGTH_HAUSF
Q_NIL_STRGTH_HAYSF
Q_NIL_STRGTH_KEP
Q_NIL_STRGTH_KIDSF
Q_NIL_STRGTH_MEWF
Q_NIL_STRGTH_RUGSF
Q_NIL_STRGTH_RRSF
Q_NIL_STRGTH_SMSF
Q_NIL_STRGTH_WHTSF

AEMO Operations
99413CONSTRAINTS24/06/2022 01:18:44 PM

Update to SA to Victoria limits for Para SVC outage

AEMO ELECTRICITY MARKET NOTICE

AEMO has been working with ElectraNet on a review of the oscillatory stability limits for the Para SVC outage for flows from South Australia to Victoria.

From that review the these limits from SA to Vic have been increased by 50 MW. The limit on Heywood has changed to 470 MW and for Heywood + Murraylink to 620 MW when the oscillatory stability monitoring is in service. If oscillatory monitoring is not in service the 50 MW increase will not apply.

The revised constraints were implemented in the constraint set S-PA_VC1 at 1300 hrs Friday 24th June 2022:
S:VS_PASVC_570OSC_AT
S:VS_PA_SVC_620
S:V_PASVC_420OSC_AT
S:V_PA_SVC_470
SV_470_DYN

AEMO and ElectraNet are continuing their studies on the limits for the Para SVC outage to determine if further increases can be made.

For further details on this this change please contact ben.blake@aemo.com.au

Ben Blake
AEMO Operations
95690CONSTRAINTS01/04/2022 09:00:20 AM

Update to Vic to NSW transient stability limit

AEMO ELECTRICITY MARKET NOTICE

AEMO has completed a comprehensive review of the system normal transient stability limit for loss of a Hazelwood to South Morang 500 kV line for flows from Victoria to New South Wales. The revised limit takes into account a larger range of inertias, demands, interconnector flows and many different plants online. The revised limit is generally lower than the existing limit due to lower demands and inertias in the Victorian system since the last review back in 2016. However, it is expected the revised limit will normally be under-cut by the Victorian export voltage collapse limit for loss of all APD potlines.

The revised constraint equation includes generators in southern NSW and generation in Victoria on the left-hand side as well as interconnectors. Full details on the limits advice are to be published on 04/04/2022 on the AEMO website: https://aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This revised limit will be implemented to the Victorian system normal constraint set V-NIL at 1000 hrs Tuesday 5th April 2022, with the following changes:

Constraint equations to remove:
- V::N_NIL_V
- V::N_NIL_S
- V::N_NIL_Q1
- V::N_NIL_Q2
Constraint equations to add:
- V::N_NIL_V1
- V::N_NIL_V2
- V::N_NIL_O1
- V::N_NIL_O2

These constraint equation changes have already been applied in AEMO's PreProduction systems.

For further details on the constraint equations please contact terry.liu@aemo.com.au

Terry Liu
AEMO Operations
93862CONSTRAINTS14/01/2022 04:02:41 PM

Updated generator combinations for SA

AEMO MARKET NOTICE

Refer to market notice 92769

AEMO has published new generator combinations for South Australia:
- 1 for four synchronous condenser operation
- 9 for two synchronous condenser operation

Details on the new combinations and conditions for their use is in the updated limits advice (which was published earlier today):
https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

For further details please contact ben.blake@aemo.com.au

Ben Blake
AEMO Operations
93841CONSTRAINTS13/01/2022 01:22:58 PM

Update to System strength requirements in North Queensland

AEMO ELECTRICITY MARKET NOTICE

Refer to market notice 89836

AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of Haughton syncon, the system normal equations have been revised.

A revision to the constraint equations will be implemented at 0900hrs on Friday 14th January 2022.

The new combinations have now published in a limits advice document on AEMO's website: For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases.

The constraint equation in the Q-NIL set of the form below will be modified:

Q_NIL_STRGTH_CLRSF
Q_NIL_STRGTH_COLSF
Q_NIL_STRGTH_DAYSF
Q_NIL_STRGTH_HAMSF
Q_NIL_STRGTH_HAUSF
Q_NIL_STRGTH_HAYSF
Q_NIL_STRGTH_KEP
Q_NIL_STRGTH_KIDSF
Q_NIL_STRGTH_MEWF
Q_NIL_STRGTH_RUGSF
Q_NIL_STRGTH_RRSF
Q_NIL_STRGTH_SMSF
Q_NIL_STRGTH_WHTSF


For further details please contact James Lindley at james.lindley@aemo.com.au or Simon Taylor at businessdevelopment@powerlink.com.au

AEMO Operations