Market Notices

115392SETTLEMENTS RESIDUE29/02/2024 05:50:23 PM

[EventId:202402291750_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 February 2024 17:50

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1750 hrs on 29 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 February 2024.

Refer to market notice: 115380

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1750 hrs on 29 February 2024.

This is an AEMO autogenerated Market Notice.
     
115380SETTLEMENTS RESIDUE29/02/2024 04:42:32 PM

[EventId:202402291640_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 February 2024 16:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1640 hrs on 29 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1640 hrs on 29 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
115377SETTLEMENTS RESIDUE29/02/2024 04:31:24 PM

[EventId:202402291630_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 February 2024 16:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1630 hrs on 29 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 February 2024.

Refer to market notice: 115369

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1630 hrs on 29 February 2024.

This is an AEMO autogenerated Market Notice.
     
115369SETTLEMENTS RESIDUE29/02/2024 02:40:34 PM

[EventId:202402291440_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 February 2024 14:40

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1440 hrs on 29 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1440 hrs on 29 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
115368SETTLEMENTS RESIDUE29/02/2024 02:30:28 PM

[EventId:202402291430_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 29 February 2024 14:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1430 hrs on 29 February 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 February 2024.

Refer to market notice: 115360

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1430 hrs on 29 February 2024.

This is an AEMO autogenerated Market Notice.
     
115360SETTLEMENTS RESIDUE29/02/2024 01:35:28 PM

[EventId:202402291335_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 29 February 2024 13:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1335 hrs on 29 February 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 29 February 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1335 hrs on 29 February 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
115357RESERVE NOTICE29/02/2024 11:24:12 AM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115351 is cancelled at 1115 hrs 29/02/2024.

Manager NEM Real Time Operations
115351RESERVE NOTICE29/02/2024 07:47:48 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No.115348 has been updated at 0745 hrs to the following:

[1.] From 1630 hrs 29/02/2024 to 1800 hrs 29/02/2024.
The forecast capacity reserve requirement is 736 MW.
The minimum capacity reserve available is 616 MW.


AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
115348RESERVE NOTICE29/02/2024 12:50:10 AM

PDPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115303 has been updated at 0050 hrs to the following:

[1.] From 1630 hrs 29/02/2024 to 1800 hrs 29/02/2024.
The forecast capacity reserve requirement is 690 MW.
The minimum capacity reserve available is 584 MW.

AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations