Market Notices

115234RESERVE NOTICE27/02/2024 06:45:02 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115204 has been updated at 1845 hrs 27/02/2024 to the following:

From 1430 hrs 29/02/2024 to 2030 hrs 29/02/2024.
The forecast capacity reserve requirement is 1332 MW.
The minimum capacity reserve available is 142 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
115208RESERVE NOTICE27/02/2024 01:00:54 PM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the QLD region advised in AEMO Electricity Market Notice No. 115203 has been updated at 1200 hrs 27/02/2024 to the following:

From 1730 hrs to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 771 MW.
The minimum capacity reserve available is 578 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115204RESERVE NOTICE27/02/2024 10:58:37 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115201 has been updated at 1000 hrs 27/02/2024 to the following:

From 1430 hrs 29/02/2024 to 2130 hrs 29/02/2024.
The forecast capacity reserve requirement is 1341 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115203RESERVE NOTICE27/02/2024 10:57:33 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the QLD Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the QLD region for the following period:

From 1730 hrs to 2000 hrs 29/02/2024.
The forecast capacity reserve requirement is 745 MW.
The minimum capacity reserve available is 336 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115201RESERVE NOTICE27/02/2024 10:17:34 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115197 has been updated at 0900 hrs 27/02/2024 to the following:

From 1430 hrs to 2100 hrs 29/02/2024.
The forecast capacity reserve requirement is 1329 MW.
The minimum capacity reserve available is 364 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115197RESERVE NOTICE27/02/2024 08:49:08 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115193 has been updated at 0800 hrs 27/02/2024 to the following:

From 1430 hrs to 2100 hrs 29/02/2024.
The forecast capacity reserve requirement is 1316 MW.
The minimum capacity reserve available is 16 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
115196RECALL GEN CAPACITY27/02/2024 08:27:52 AM

Request for Generator Recall Information for 29/02/2024 for QLD Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193. Additional generation in QLD could assist in alleviating the forecast LOR2 condition in NSW.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
115195RECALL GEN CAPACITY27/02/2024 08:26:49 AM

Request for Generator Recall Information for 29/02/2024 for NSW Region

AEMO ELECTRICITY MARKET NOTICE

Refer to AEMO Electricity Market Notice no. 115193.

Please provide Generator Recall Information for the period 29/02/2024, by 1200 hrs 28/02/2024 via the Generator Recall communication system, in accordance with clause 4.8.5A of the National Electricity Rules.

SO_OP_3719 Procedure for Submitting Generator Outage Recall Information is available at:
https://aemo.com.au/-/media/files/electricity/nem/security_and_reliability/power_system_ops/procedures/so_op_3719-procedure-for-submitting-recall-information-scheduled-generator-outages.pdf

Procedure on how to use Generator Recall in the EMMS Markets Portal is available at
http://www.aemo.com.au/-/media/Files/Electricity/NEM/IT-Systems-and-Change/2018/Guide-to-Generator-Recall-Plans.pdf

AEMO Operations
115193RESERVE NOTICE27/02/2024 08:02:34 AM

STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 29/02/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 115190 has been updated at 0700 hrs 27/02/2024 to the following:

From 1500 hrs to 2100 hrs 29/02/2024.
The forecast capacity reserve requirement is 1318 MW.
The minimum capacity reserve available is 264 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations