Market Notices

110677CONSTRAINTS02/11/2023 10:53:49 AM

Update to voltage stability and system strength constraints in North Queensland

AEMO ELECTRICITY MARKET NOTICE


Refer to market notice 102074


AEMO and Powerlink are continuing to investigate system strength requirements in North Queensland.
Due to commissioning of new feeder 8905 (H13 Ross - H39 Woree) 275kV line in Far North Queensland, the system normal equations for system strength and voltage stability have been revised.

A revision to the constraint equations will be implemented at 1400 hrs on Thursday 2nd November 2023.

The new system strength combinations have now published in a limits advice document on AEMO's website. For more information refer to the new limits advice: https://www.aemo.com.au/energy-systems/electricity/national-electricity-market-nem/system-operations/congestion-information-resource/limits-advice

This advice contains all the combinations for Queensland for system normal cases.

The constraint equations in the Q-NIL set below will be modified:

? Q_NIL_STRGTH_KBWF
? Q_NIL_STRGTH_KBWF
? Replace Q^NIL_FNQ_MEWF and Q^NIL_FNQ_WRSVC with new equation Q^NIL_FNQ_8905

AEMO Operations
110560RESERVE NOTICE27/10/2023 08:20:02 PM

Cancellation of Actual (LOR2) condition in the SA region - 27/10/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the SA region - 27/10/2023

The Actual LOR2 Condition in the SA Region advised in AEMO Electricity Market Notice No.110559 is cancelled at 2015 hrs 27/10/2023.

Manager NEM Real Time Operations
110559RESERVE NOTICE27/10/2023 07:49:02 PM

Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 27/10/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the SA region - 27/10/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the SA region from 1930 hrs.
The Actual LOR2 condition is not forecast in Pre Dispatch

The capacity reserve required is 480 MW
The minimum reserve available is 465 MW

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement a AEMO intervention event.

Manager NEM Real Time Operations
108172RESERVE NOTICE25/05/2023 08:46:48 PM

Update - PDPASA - Cancellation of the Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 108160 is cancelled at 2045 hrs 25/05/2023.

Manager NEM Real Time Operations
108165RESERVE NOTICE25/05/2023 08:45:53 PM

PDPASA - Cancellation of the Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023

AEMO ELECTRICITY MARKET NOTICE

The Actual LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 108160 is cancelled at 2145 hrs 25/05/2023.

Manager NEM Real Time Operations
108160RESERVE NOTICE25/05/2023 08:19:28 PM

Actual Lack Of Reserve Level 2 (LOR2) in the NSW Region on 25/05/2023

AEMO ELECTRICITY MARKET NOTICE

Actual Lack Of Reserve Level 2 (LOR2) in the NSW region - 25/05/2023

An Actual LOR2 condition has been declared under clause 4.8.4(b) of the National Electricity Rules for the NSW region from 2000 hrs.

The Actual LOR2 condition is forecast to exist until 2030 hrs.

The forecast capacity reserve requirement is 851 MW.
The minimum capacity reserve available is 767 MW.

AEMO is seeking an immediate market response.

An insufficient market response may require AEMO to implement an AEMO intervention event.

Manager NEM Real Time Operations
107205CONSTRAINTS03/04/2023 01:42:00 PM

Tasmanian Regulation FCAS changes - Wednesday 5th April 2023

AEMO ELECTRICITY MARKET NOTICE

AEMO are changing the procurement of Regulation FCAS for the TAS region.

This change is based on advice received from TasNetworks, following a review of operation of the TAS region with the end of the reclassification of Basslink.

Refer to AEMO Electricity market notice 105443.

Following this change Regulation FCAS requirements for the TAS region will only be procured from within TAS.

This change will be implemented from 1000 on Wed 5th April.

Ben Blake
Manager Congestion & Grid Modelling
106855CONSTRAINTS21/03/2023 08:14:08 AM

Update to Victorian system normal constraint equations ID

AEMO ELECTRICITY MARKET NOTICE

AEMO has been conducting major review of thermal constraint equations for preparation of completion of VNI East project. As part of the review, AEMO is going to update the constraint equations IDs to use the new standard format of below (this is the same standard now used in NSW):

V>>[OUTAGE]_[MONITORING ELEMENT]_[CONTINGENCY ELEMENT]

This is to improve the simplicity and readability of a thermal constraint equation ID.

Constraint equations ID in sets V-NIL and V-NIL_BATS_BETS_15M will be updated to the new format on Thursday 23rd March 2023 at 1000 hrs. The previous used constraint equations ID will be included in the Modification field of the constraint equation for reference.

The changes have now been implemented into AEMO's pre-production system.

Terry Liu
AEMO Operations
106726RESERVE NOTICE16/03/2023 06:57:37 PM

Cancellation of Actual (LOR2) condition in the NSW region - 16/03/2023

AEMO ELECTRICITY MARKET NOTICE

Cancellation of Actual (LOR2) condition in the NSW region - 16/03/2023

The Actual LOR2 Condition in the NSW Region advised in AEMO Electricity Market Notice No.106716 is cancelled at 1855hrs 16/03/2023

Manager NEM Real Time Operations