Filter by category
Filter by Date
Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025
Inter-regional transfer limit variation - Darlington Point - Wagga No.63 330 kV line - NSW region - 23/06/2025
At 1719 hrs 23/06/2025 there was an unplanned outage of Darlington Point - Wagga No.63 330 kV line. The Darlington Point - Balranald No. X5 220 kV line consequently tripped due to a control scheme for the trip of the above line as per design.
The following constraint set(s) invoked at 1725 hrs 23/06/2025
N-DPWG_63_X5
This constraint set(s) contains equations with the following interconnectors on the LHS.
VIC1-NSW1,N-Q-MNSP1,NSW1-QLD1,V-S-MNSP1,V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
[EventId:202506231410_review] Prices for interval 23-Jun-2025 14:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 1405 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231405_review] Prices for interval 23-Jun-2025 14:05 are subject to review
Issued by Australian Energy Market Operator Ltd at 1400 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:05.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231400_review] Prices for interval 23-Jun-2025 14:00 are subject to review
Issued by Australian Energy Market Operator Ltd at 1355 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 14:00.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0000 hrs to 0300 hrs 01/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 205 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202506231355_review] Prices for interval 23-Jun-2025 13:55 are subject to review
Issued by Australian Energy Market Operator Ltd at 1350 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:55.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 30/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
1. From 0730 hrs to 1000 hrs 30/06/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 136 MW.
2. From 1700 hrs to 2359 hrs 30/06/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 109 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
[EventId:202506231350_review] Prices for interval 23-Jun-2025 13:50 are subject to review
Issued by Australian Energy Market Operator Ltd at 1345 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:50.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202506231345_review] Prices for interval 23-Jun-2025 13:45 are subject to review
Issued by Australian Energy Market Operator Ltd at 1340 hrs on 23 June 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 23-Jun-2025 13:45.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.