Market Notices

127850RESERVE NOTICE25/06/2025 02:48:53 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0000 hrs to 0400 hrs 03/07/2025.
The forecast capacity reserve requirement is 236 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127849RESERVE NOTICE25/06/2025 02:48:33 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0400 hrs to 0630 hrs 02/07/2025.
The forecast capacity reserve requirement is 242 MW.
The minimum capacity reserve available is 0 MW.

2. From 1100 hrs to 1230 hrs 02/07/2025.
The forecast capacity reserve requirement is 231 MW.
The minimum capacity reserve available is 7 MW.

3. From 1600 hrs to 1700 hrs 02/07/2025.
The forecast capacity reserve requirement is 248 MW.
The minimum capacity reserve available is 0 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127844MARKET INTERVENTION25/06/2025 02:02:08 PM

Cancellation - AEMO Intervention Event - SA region 21/06/2025

AEMO ELECTRICITY MARKET NOTICE

Cancellation - AEMO Intervention Event - SA region 21/06/2025

Refer to Market Notice 127682

The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 25/06/2025.


Manager NEM Real Time Operations
     
127843MARKET INTERVENTION25/06/2025 02:01:53 PM

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

AEMO ELECTRICITY MARKET NOTICE

Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN

Refer to Market Notice 127792

Direction is cancelled from: 1400 hrs 25/06/2025

Manager NEM Real Time Operations
     
127840RESERVE NOTICE25/06/2025 12:02:06 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127819 and Market Notice No. 127782 is cancelled at 1100 hrs 25/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127839RESERVE NOTICE25/06/2025 12:01:51 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127818 is cancelled at 1100 hrs 25/06/2025.

No LOR2 condition is currently forecast in the STPASA period.

AEMO Operations
     
127829SETTLEMENTS RESIDUE24/06/2025 09:30:24 PM

[EventId:202506242130_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 21:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2130 hrs on 24 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Refer to market notice: 127824

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 2130 hrs on 24 June 2025.

This is an AEMO autogenerated Market Notice.
     
127824SETTLEMENTS RESIDUE24/06/2025 08:35:21 PM

[EventId:202506242035_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 June 2025 20:35

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2035 hrs on 24 June 2025

ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.

The negative residue constraint set NRM_VIC1_SA1 commenced operating from 2035 hrs on 24 June 2025.

This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
127823SETTLEMENTS RESIDUE24/06/2025 08:00:35 PM

[EventId:202506242000_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 20:00

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 2000 hrs on 24 June 2025

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.

Refer to market notice: 127821

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.

The negative residue constraint NRM_VIC1_SA1 ceased operating at 2000 hrs on 24 June 2025.