Market Notices

116798MARKET INTERVENTION24/05/2024 04:00:08 PM

Direction - SA region 24/05/2024

AEMO ELECTRICITY MARKET NOTICE.

Direction - SA region 24/05/2024

In accordance with section 116 of the National Electricity Law, AEMO has issued a direction to a participant in the SA region. For the purposes of the National Electricity Rules this is a direction under clause 4.8.9(a).

The direction was necessary to maintain the power system in a secure operating state.

AEMO may issue or revoke additional directions in order to meet the current requirement, unless sufficient market response is provided. A further market notice will be issued when all directions related to this requirement have been cancelled.

The issue of the direction commences an AEMO intervention event. AEMO declares all trading intervals during the event to be intervention trading intervals, commencing from the interval ending 1605 hrs on 24/05/2024.

Intervention pricing does not apply to this AEMO intervention event.

Manager NEM Real Time Operations
     
116795MARKET INTERVENTION24/05/2024 03:20:00 PM

Update - Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Update - Possible intervention to manage power system security in SA region

Refer AEMO Electricity Market Notice 116794

The synchronous generating units currently expected to be synchronised in SA from 1000 hrs 25/05/2024 will be inadequate to maintain a secure operating state in SA .

AEMO estimates that, in the absence of sufficient market response by 1600 hrs 24/05/2024, AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116794MARKET INTERVENTION24/05/2024 01:33:55 PM

Possible intervention to manage power system security in SA region

AEMO ELECTRICITY MARKET NOTICE

Possible intervention to manage power system security in SA region

The synchronous generating units currently expected to be synchronised in SA from 0930 hrs 25/05/2024 will be inadequate to maintain a secure operating state in SA.
AEMO may need to intervene by issuing a direction requiring one or more SA synchronous generating unit(s) to operate or remain synchronised to maintain power system security in SA.

Manager NEM Real Time Operations
     
116737RESERVE NOTICE21/05/2024 03:29:47 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 23/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116724 is cancelled at 1400 hrs 21/05/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
116736RESERVE NOTICE21/05/2024 03:30:30 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 22/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116723 is cancelled at 1400 hrs 21/05/2024.

No LOR condition is currently forecast in the STPASA period.

AEMO Operations
     
116732SETTLEMENTS RESIDUE20/05/2024 06:30:21 PM

[EventId:202405201830_NRM_NSW1_VIC1_stopped] NEGRES CONSTRAINT NRM_NSW1_VIC1 ceased operating from 20 May 2024 18:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1830 hrs on 20 May 2024

CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 May 2024.

Refer to market notice: 116731

AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the NSW to VIC directional interconnector.

The negative residue constraint NRM_NSW1_VIC1 ceased operating at 1830 hrs on 20 May 2024.

This is an AEMO autogenerated Market Notice.
     
116731SETTLEMENTS RESIDUE20/05/2024 05:30:23 PM

[EventId:202405201730_NRM_NSW1_VIC1_started] NEGRES CONSTRAINT NRM_NSW1_VIC1 started operating from 20 May 2024 17:30

AEMO ELECTRICITY MARKET NOTICE

Issued by Australian Energy Market Operator Ltd at 1730 hrs on 20 May 2024

ACTUAL NEGATIVE SETTLEMENT RESIDUES - NSW to VIC - 20 May 2024.

Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the NSW to VIC directional interconnector.

The negative residue constraint set NRM_NSW1_VIC1 commenced operating from 1730 hrs on 20 May 2024.

This constraint set contains an equation with the following interconnectors on the LHS:
VIC1-NSW1

The RHS of the constraint equation may be adjusted to manage residues.


This is an AEMO autogenerated Market Notice.
     
116728RESERVE NOTICE20/05/2024 03:58:09 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 21/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No. 116722 for the 21/05/2024 is cancelled at 1600 hrs 20/05/2024.

Manager NEM Real Time Operations
     
116725RESERVE NOTICE20/05/2024 02:56:01 PM

PDPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 20/05/2024

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the NSW region advised in AEMO Electricity Market Notice No.116700 has been updated at 1450 hrs to the following:

[1.] From 1630 hrs 20/05/2024 to 1900 hrs 20/05/2024.
The forecast capacity reserve requirement is 1630 MW.
The minimum capacity reserve available is 958 MW.

Manager NEM Real Time Operations
     