Planned outage of Dapto - Kangaroo Valley (18) 330 kV line in the NSW region on 20/07/2025
The Dapto - Kangaroo Valley (18) 330 kV line in the New South Wales (NSW) region is planned to be out of service from 0615 hrs to 1630 hrs 20/07/2025.
This outage is considered as a High Impact Outage (HIO).
During this planned outage:
- There is a potential for Energy and FCAS prices to approach the Market Price Cap.
- Power transfer will be restricted between VIC/Snowy and NSW.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
Non-credible contingency event - QLD region - 18/07/2025
Non-credible contingency event - QLD region - 18/07/2025
At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.
AEMO did not instruct load shedding.
AEMO has not been advised of any disconnection of bulk electrical load.
The cause of this non credible contingency event is not known at this stage.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 18 July 2025
NON-CONFORMANCE QLD1 Region Friday, 18 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: DDPS1
Duration: 18/07/2025 06:25 to 18/07/2025 06:30
Amount: -14 MW
Constraint: NC-Q_DDPS1
Auto-generated on behalf of Manager NEM Real Time Operations
[EventId:202507162235_review] Prices for interval 16-Jul-2025 22:35 are subject to review
Issued by Australian Energy Market Operator Ltd at 2230 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:35.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162230_review] Prices for interval 16-Jul-2025 22:30 are subject to review
Issued by Australian Energy Market Operator Ltd at 2225 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:30.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162225_review] Prices for interval 16-Jul-2025 22:25 are subject to review
Issued by Australian Energy Market Operator Ltd at 2220 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:25.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162220_review] Prices for interval 16-Jul-2025 22:20 are subject to review
Issued by Australian Energy Market Operator Ltd at 2215 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:20.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162215_review] Prices for interval 16-Jul-2025 22:15 are subject to review
Issued by Australian Energy Market Operator Ltd at 2210 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:15.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.
[EventId:202507162210_review] Prices for interval 16-Jul-2025 22:10 are subject to review
Issued by Australian Energy Market Operator Ltd at 2205 hrs on 16 July 2025
PRICES ARE SUBJECT TO REVIEW for trading interval 16-Jul-2025 22:10.
AEMO is reviewing these prices in accordance with:
- Clause 3.9.2B of the National Electricity Rules for Manifestly Incorrect Inputs
This is an AEMO autogenerated Market Notice.