Planned outage of Dapto - Kangaroo Valley (18) 330 kV line in the NSW region on 20/07/2025
The Dapto - Kangaroo Valley (18) 330 kV line in the New South Wales (NSW) region is planned to be out of service from 0615 hrs to 1630 hrs 20/07/2025.
This outage is considered as a High Impact Outage (HIO).
During this planned outage:
- There is a potential for Energy and FCAS prices to approach the Market Price Cap.
- Power transfer will be restricted between VIC/Snowy and NSW.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025
Inter-regional transfer limit variation - S3 Greenbank 275 kV SVC - QLD region - 18/07/2025
At 1207 hrs 18/07/2025 there was an unplanned outage of S3 Greenbank 275 kV SVC.
The following constraint set(s) invoked at 1215 hrs 18/07/2025
Q-GB_VC
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1,N-Q-MNSP1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025
Inter-regional transfer limit variation - Calvale-Halys 8810 275kV LINE - QLD region - 17/07/2025
A planned outage of Calvale-Halys 8810 275kV LINE in the QLD region was scheduled from 2300 hrs 15/07/2025 to 1600 hrs 18/07/2025.
The outage has been completed and Calvale-Halys 8810 275kV LINE returned to service at 1500 hrs 17/07/2025
Constraint set(s) revoked: Q-HACL
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Heywood M1 Transformer - VIC region - 16/07/2025
Inter-regional transfer limit variation - Heywood M1 Transformer- VIC region - 16/07/2025
A planned outage of Heywood M1 Transformer in the VIC region was scheduled from 0700 hrs 16/07/2025 to 1800 hrs 16/07/2025.
The outage has been completed and Heywood M1 Transformer returned to service at 1335 hrs 16/07/2025
Constraint set(s) revoked: V-HYTX_M12
Manager NEM Real Time Operations
Network Augmentation Commissioned - NSW Region - 14/07/2025
Network Augmentation Commissioned - NSW Region - 14/07/2025
Commissioned:
Buronga No. 1 330 kV/330 kV phase shifting transformer
Buronga No. 2 330 kV/330 kV phase shifting transformer
Buronga No. 3 330 kV/330 kV phase shifting transformer
Buronga No. 4 330 kV/330 kV phase shifting transformer
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 3 Leg of Directlink .
The following constraint set was invoked at 2255 hrs 12/07/2025
N-X_MBTE_3
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
Inter-regional transfer limit variation - Braemar (R2) No.1 330/275 kV Transformer - QLD region - 12/07/2025
Inter-regional transfer limit variation - Braemar (R2) No.1 330/275 kV Transformer - QLD region - 12/07/2025
At 2145 hrs 12/07/2025 there was an unplanned outage of Braemar (R2) No.1 330/275 kV Transformer.
The following constraint set(s) invoked at 2145 hrs 12/07/2025
Q-BRTX1
This constraint set(s) contains equations with the following interconnectors on the LHS.
NSW1-QLD1
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Inter-Regional Transfer limit variation - Directlink - NSW Region
Inter-Regional Transfer limit variation - Directlink - NSW Region
There has been an unplanned outage of the No 2 Leg of Directlink .
The following constraint set was invoked at 1350 hrs 12/07/2025
N-X_MBTE_2
The constraint set contains the following interconnector on the left hand side.
N-Q-MNSP1
Refer AEMO Network Outage Scheduler (NOS) for further details.
Manager NEM Real Time Operations
[EventId:202507092030_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 09 July 2025 20:30
Issued by Australian Energy Market Operator Ltd at 2030 hrs on 9 July 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 9 July 2025.
Refer to market notice: 128067
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 2030 hrs on 9 July 2025.
This is an AEMO autogenerated Market Notice.