128457RESERVE NOTICE06/08/2025 03:16:12 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 128455 is cancelled at 1515 hrs 06/08/2025.

Manager NEM Real Time Operations
     
128456RESERVE NOTICE06/08/2025 03:07:57 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.

AEMO Operations
     
128455RESERVE NOTICE06/08/2025 01:25:22 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:


[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.


Manager NEM Real Time Operations
     
128454MARKET SYSTEMS06/08/2025 11:20:34 AM

Completed - CHG0105078 - Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade

Change Number: CHG0105078

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd

Change Title: Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
128447NON-CONFORMANCE05/08/2025 04:55:17 PM

NON-CONFORMANCE Region SA1 Tuesday, 5 August 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Tuesday, 5 August 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: HPR1
Duration: 05/08/2025 16:50 to 05/08/2025 16:55
Amount: 13 MW
Constraint: NC-S_HPR1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128430RESERVE NOTICE04/08/2025 02:40:03 PM

STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the TAS region for the following period:

From 0730 hrs to 0830 hrs 07/08/2025.
The forecast capacity reserve requirement is 582 MW.
The minimum capacity reserve available is 549 MW.

AEMO Operations
     
128429MARKET SYSTEMS03/08/2025 02:38:25 PM

CHG0104554 - Production eMDM Maintenance Release

Change Number: CHG0104554

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MDM - Meter Data Management
Change Title: Production eMDM Maintenance Release

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
128428MARKET SYSTEMS03/08/2025 02:35:38 PM

CHG0102957 - Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1

Change Number: CHG0102957

Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: Gas Hub
Change Title: Roll out of TLS 1.3 support for Gas B2B Hub and disable TLS versions 1.0/1.1

Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
     
128419GENERAL NOTICE01/08/2025 06:30:34 PM

New South Wales - Waratah Super Battery System Integrity Protection Scheme (SIPS) In-Service

AEMO ELECTRICITY MARKET NOTICE.

The Waratah Super Battery System Integrity Protection Scheme (SIPS) has been enabled by TransGrid at 1758 hrs 01/08/2025.

Manager NEM Real Time Operations
     