Filter by category
Filter by Date
[EventId:202506251720_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 25 June 2025 17:20
Issued by Australian Energy Market Operator Ltd at 1720 hrs on 25 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 25 June 2025.
Refer to market notice: 127856
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 1720 hrs on 25 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506251535_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 25 June 2025 15:35
Issued by Australian Energy Market Operator Ltd at 1535 hrs on 25 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 25 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1535 hrs on 25 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
CHG0103089 - ERI & STPASA Recall Period Production Release
Notification issued to: Market Notice
Notification Type: Initial
Change Type: Normal
Service/ Component: EMMS - Dispatch
Change Title: ERI & STPASA Recall Period Production Release
Change Start Date & Time: 30/06/2025 09:00:00
Change End Date & Time: 04/07/2025 18:00:00
Outage Start Date & Time: 30/06/2025 11:45:00
Outage End Date & Time: 30/06/2025 11:55:00
Environment: Production
Participant Impact and Requirements: Under this change, AEMO will upgrade the NEMDE solver used in Production for Dispatch, 5-Minute Predispatch, Predispatch and PD7 to a new version. AEMO will also upgrade other relevant applications for Dispatch, 5-Minute Predispatch, Predispatch, PD7, Bidding, SOMMS and?Registration. This change will become effective upon rule commencement on 1 July, 2025
Impact : A Planned outage for BIDDING application is scheduled on 30th June 2025 between 11:45 AM and 11:55 AM. The application will be unavailable for approximately 5-7 min during this window.
Support Information:
Report any impacts to the AEMO Information and Support Hub or call 1300 236 600.
Please refer to https://aemo.service-now.com/participantportal?id=pp_services_status for any planned/unplanned maintenance activities.
Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025
The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.
A credible contingency event during this planned outage may require:
* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
[EventId:202506242130_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 21:30
Issued by Australian Energy Market Operator Ltd at 2130 hrs on 24 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.
Refer to market notice: 127824
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 2130 hrs on 24 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506242035_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 June 2025 20:35
Issued by Australian Energy Market Operator Ltd at 2035 hrs on 24 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 2035 hrs on 24 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.
[EventId:202506242000_NRM_VIC1_SA1_stopped] NEGRES CONSTRAINT NRM_VIC1_SA1 ceased operating from 24 June 2025 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 24 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.
Refer to market notice: 127821
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to SA directional interconnector.
The negative residue constraint NRM_VIC1_SA1 ceased operating at 2000 hrs on 24 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506242000_NRM_VIC1_NSW1_stopped] NEGRES CONSTRAINT NRM_VIC1_NSW1 ceased operating from 24 June 2025 20:00
Issued by Australian Energy Market Operator Ltd at 2000 hrs on 24 June 2025
CANCELLATION - ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to NSW - 24 June 2025.
Refer to market notice: 127820
AEMO has ceased taking action to minimize the further accumulation of negative settlement residues on the VIC to NSW directional interconnector.
The negative residue constraint NRM_VIC1_NSW1 ceased operating at 2000 hrs on 24 June 2025.
This is an AEMO autogenerated Market Notice.
[EventId:202506241910_NRM_VIC1_SA1_started] NEGRES CONSTRAINT NRM_VIC1_SA1 started operating from 24 June 2025 19:10
Issued by Australian Energy Market Operator Ltd at 1910 hrs on 24 June 2025
ACTUAL NEGATIVE SETTLEMENT RESIDUES - VIC to SA - 24 June 2025.
Electricity Market outcomes have resulted in the accumulation of negative settlement residues that have exceeded the allowable negative residue threshold for the VIC to SA directional interconnector.
The negative residue constraint set NRM_VIC1_SA1 commenced operating from 1910 hrs on 24 June 2025.
This constraint set contains an equation with the following interconnectors on the LHS:
V-S-MNSP1
V-SA
The RHS of the constraint equation may be adjusted to manage residues.
This is an AEMO autogenerated Market Notice.