Filter by category
Filter by Date
Reclassification of a Non-Credible Contingency Event: Bayswater - Mt Piper No.5A3 500kV line and Wollar - Mt Piper No.5A5 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bayswater - Mt Piper No.5A3 500kV and Wollar - Mt Piper No.5A5 500kV
Duration: 06/07/2025 15:21 until further notice
Constraint set(s) invoked:
NONE
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127957 is cancelled at 1400 hrs 06/07/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127956 is cancelled at 1400 hrs 06/07/2025.
Manager NEM Real Time Operations
Reclassification of a Non-Credible Contingency Event: Bannaby - Mt Piper 5A6 500kV line and Bannaby - Mt Piper 5A7 500kV line in NSW1 due to Lightning.
Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.
Region: NSW1
Lines: Bannaby - Mt Piper 5A6 500kV and Bannaby - Mt Piper 5A7 500kV
Duration: 06/07/2025 14:50 until further notice
Constraint set(s) invoked:
N-5A6+5A7_N-2 Constraint set contains the following interconnector(s) on the left hand side:
N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127943 has been updated to the following:
[1.] From 0000 hrs 12/07/2025 to 0330 hrs 12/07/2025.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 366 MW.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127942 has been updated to the following:
[1.] From 0400 hrs 11/07/2025 to 1200 hrs 11/07/2025.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 344 MW.
[2.] From 1630 hrs 11/07/2025 to 0000 hrs 12/07/2025.
The forecast capacity reserve requirement is 456 MW.
The minimum capacity reserve available is 340 MW.
Manager NEM Real Time Operations
NON-CONFORMANCE Region QLD1 Friday, 4 July 2025
NON-CONFORMANCE QLD1 Region Friday, 4 July 2025
AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:
Unit: TARONG#3
Duration: 04/07/2025 16:40 to 04/07/2025 16:45
Amount: -18 MW
Constraint: NC-Q_TARONG#3
Auto-generated on behalf of Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 12/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0230 hrs to 0400 hrs 12/07/2025.
The forecast capacity reserve requirement is 450 MW.
The minimum capacity reserve available is 235 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 11/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 1030 hrs to 1200 hrs 11/07/2025.
The forecast capacity reserve requirement is 449 MW.
The minimum capacity reserve available is 230 MW.
2. From 1600 hrs to 1630 hrs 11/07/2025.
The forecast capacity reserve requirement is 451 MW.
The minimum capacity reserve available is 397 MW.
AEMO Operations