STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 03/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0000 hrs to 0400 hrs 03/07/2025.
The forecast capacity reserve requirement is 236 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0400 hrs to 0630 hrs 02/07/2025.
The forecast capacity reserve requirement is 242 MW.
The minimum capacity reserve available is 0 MW.
2. From 1100 hrs to 1230 hrs 02/07/2025.
The forecast capacity reserve requirement is 231 MW.
The minimum capacity reserve available is 7 MW.
3. From 1600 hrs to 1700 hrs 02/07/2025.
The forecast capacity reserve requirement is 248 MW.
The minimum capacity reserve available is 0 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Cancellation - AEMO Intervention Event - SA region 21/06/2025
Cancellation - AEMO Intervention Event - SA region 21/06/2025
Refer to Market Notice 127682
The AEMO Intervention Event and all associated directions are cancelled from 1400 hrs on 25/06/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 127792
Direction is cancelled from: 1400 hrs 25/06/2025
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 02/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127819 and Market Notice No. 127782 is cancelled at 1100 hrs 25/06/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127818 is cancelled at 1100 hrs 25/06/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
Planned outage of Kiamal SF-Red Cliffs 220kV LINE in the VIC region on 27/06/2025
The Kiamal SF-Red Cliffs 220kV LINE line in the Victorian (VIC) region is planned to be out of service from 0700 hrs on 27/06/2025 to 1630 hrs on 27/06/2025.
A credible contingency event during this planned outage may require:
* Load shedding in the Victorian outer grid; and/ or
* Market intervention, such as the issuing of directions.
Refer AEMO Network Outage Schedule (NOS) for further details.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region beginning on 02/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0000 hrs 02/07/2025 to 0400 hrs 02/07/2025.
The forecast capacity reserve requirement is 239 MW.
The minimum capacity reserve available is 193 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025
The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 127812 has been updated at 1830 hrs 24/06/2025 to the following:
[1.] From 0400 hrs 01/07/2025 to 1000 hrs 01/07/2025.
The forecast capacity reserve requirement is 230 MW.
The minimum capacity reserve available is 123 MW.
2. From 1700 hrs to 2359 hrs 01/07/2025.
The forecast capacity reserve requirement is 234 MW.
The minimum capacity reserve available is 97 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations