128378NON-CONFORMANCE26/07/2025 09:25:25 PM

NON-CONFORMANCE Region QLD1 Saturday, 26 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Saturday, 26 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ULPBESS1
Duration: 26/07/2025 21:15 to 26/07/2025 21:25
Amount: 6 MW
Constraint: NC-Q_ULPBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128375NON-CONFORMANCE26/07/2025 02:05:19 PM

NON-CONFORMANCE Region VIC1 Saturday, 26 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 26 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: KESSB1
Duration: 26/07/2025 13:40 to 26/07/2025 14:05
Amount: 55 MW
Constraint: NC-V_KESSB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128374NON-CONFORMANCE26/07/2025 01:00:19 PM

NON-CONFORMANCE Region VIC1 Saturday, 26 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Saturday, 26 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: RANGEB1
Duration: 26/07/2025 12:45 to 26/07/2025 13:00
Amount: 102 MW
Constraint: NC-V_RANGEB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128317RESERVE NOTICE25/07/2025 03:07:49 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 28/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128313 is cancelled at 1400 hrs 25/07/2025.

No LOR condition is currently forecast in the STPASA period.


AEMO Operations
     
128313RESERVE NOTICE25/07/2025 10:27:08 AM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 28/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 0730 hrs to 0900 hrs 28/07/2025.
The forecast capacity reserve requirement is 563 MW.
The minimum capacity reserve available is 536 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.


AEMO Operations
     
128296RESERVE NOTICE24/07/2025 02:07:32 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 25/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128289 is cancelled at 0200 hrs 24/07/2025.

Manager NEM Real Time Operations
     
128289RESERVE NOTICE23/07/2025 04:32:09 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 25/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:

From 1400 hrs to 1430 hrs 25/07/2025.
The forecast capacity reserve requirement is 778 MW.
The minimum capacity reserve available is 777 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
128277RESERVE NOTICE23/07/2025 02:10:12 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 25/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR2 condition in the SA region advised in AEMO Electricity Market Notice No. 128259 is cancelled at 0200 hrs 23/07/2025.

Manager NEM Real Time Operations
     
128259RESERVE NOTICE22/07/2025 04:34:09 PM

STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 25/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0800 hrs to 1000 hrs 25/07/2025.
The forecast capacity reserve requirement is 830 MW.
The minimum capacity reserve available is 790 MW.

2. From 1030 hrs to 1130 hrs 25/07/2025.
The forecast capacity reserve requirement is 846 MW.
The minimum capacity reserve available is 798 MW.

3. From 1300 hrs to 1330 hrs 25/07/2025.
The forecast capacity reserve requirement is 842 MW.
The minimum capacity reserve available is 837 MW.

4. From 1400 hrs to 1530 hrs 25/07/2025.
The forecast capacity reserve requirement is 839 MW.
The minimum capacity reserve available is 804 MW.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.

AEMO Operations
     
X
Cookies help us improve your website experience.
By using our website, you agree to our use of cookies.
Confirm