128160POWER SYSTEM EVENTS18/07/2025 08:49:29 AM

Non-credible contingency event - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 18/07/2025

At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
127864RESERVE NOTICE25/06/2025 04:58:25 PM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127847 is cancelled at 1600 hrs on 25/06/2025.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
127847RESERVE NOTICE25/06/2025 02:48:13 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 02/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:

1. From 0630 hrs to 1100 hrs 02/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 108 MW at 0800 hrs.

2. From 1700 hrs 02/07/2025 to 0000 hrs 03/07/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 153 MW at 1900 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

AEMO Operations
     
127773RESERVE NOTICE24/06/2025 09:45:42 AM

STPASA - Cancellation of the Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR3 condition in the SA region advised in AEMO Electricity Market Notice No. 127753 is cancelled at 0900 hrs on 24/06/2025.

No LOR3 condition is currently forecast in the STPASA period.

AEMO Operations
     
127753RESERVE NOTICE23/06/2025 09:53:46 PM

STPASA - Forecast Lack Of Reserve Level 3 (LOR3) in the SA Region on 30/06/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR3 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period[s]:

[1.] From 0730 hrs 30/06/2025 to 0930 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 87 MW at 0800 hrs.

[2.] From 1700 hrs 30/06/2025 to 2300 hrs 30/06/2025.
The maximum load (other than interruptible loads) forecast to be interrupted is 112 MW at 1900 hrs.

AEMO is seeking a market response.

AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.

Manager NEM Real Time Operations
     
127502POWER SYSTEM EVENTS15/06/2025 11:14:11 AM

Update - Non-credible contingency event - QLD region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 11/06/2025

Refer AEMO Electricity Market Notice 127500

At 1050 hrs the Belmont - Loganlea 829 275 kV line was returned to service and previously (11/06/25) the Belmont (H3) No. 1 275 kV bus had returned to service.

The cause of this non-credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     
127500POWER SYSTEM EVENTS11/06/2025 06:05:55 PM

Update - Non-credible contingency event - QLD region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Update - Non-credible contingency event - QLD region - 11/06/2025

Refer AEMO Electricity Market Notice 127499

At 1713 hrs the Belmont (H3) No.1 275 kV bus and Loganlea - Belmont (829) 275 kV line tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
127499POWER SYSTEM EVENTS11/06/2025 05:24:51 PM

Non-credible contingency event - QLD region - 11/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 11/06/2025

At 1713 hrs the Belmont (H3) No.1 275 kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.


Manager NEM Real Time Operations
     
127406POWER SYSTEM EVENTS06/06/2025 08:43:55 AM

Non-credible contingency event - VIC region - 06/06/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 06/06/2025

At 0830 hrs the Wodonga No 2 330kV bus tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event has been identified and AEMO is satisfied that another occurrence of this event is unlikely under the current circumstances.

AEMO will not reclassify this event as a credible contingency event.

Manager NEM Real Time Operations
     