Filter by category
Filter by Date
PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
The Forecast LOR1 condition in the VIC region advised in AEMO Electricity Market Notice No. 128455 is cancelled at 1515 hrs 06/08/2025.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the TAS Region on 07/08/2025
The Forecast LOR1 condition in the TAS region advised in AEMO Electricity Market Notice No. 128430 is cancelled at 1400 hrs 06/08/2025.
AEMO Operations
PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the VIC Region on 07/08/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the VIC region for the following Period:
[1.] From 0730 hrs 07/08/2025 to 0800 hrs 07/08/2025.
The forecast capacity reserve requirement is 1148 MW.
The minimum capacity reserve available is 942 MW.
Manager NEM Real Time Operations
Completed - CHG0105078 - Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Notification issued to: Market Notice
Notification Type: Completed
Change Type: Normal
Service/Component: MSATS - Consumer Administration and Transfer Solution(CATS)_PreProd
Change Title: Pre-Prod MSATS Maintenance Release for webMethods 11.1 upgrade
Support Information: Report any impacts to the AEMO Information and Support Hub or on External 1300 236 600.
Inter-regional transfer limit variation - Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE - VIC region - 06/08/2025
Inter-regional transfer limit variation - Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE - VIC region - 06/08/2025
A planned outage of Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE in the VIC region was scheduled from 0700 hrs 06/08/2025 to 1800 hrs 06/08/2025.
The outage has been completed and Red Cliffs - Wemen 220kV LINE and Koorangie - Wemen 220kV LINE returned to service at 0945 hrs 06/08/2025
Constraint set(s) revoked: V-KO_WE_RC
Manager NEM Real Time Operations
Inter-regional transfer limit variation - South East 275 kV No. 2 SVC - SA region - 05/08/2025
Inter-regional transfer limit variation - South East 275 kV No. 2 SVC - SA region - 05/08/2025
At 2036 hrs 05/08/2025 there was an unplanned outage of South East 275 kV No. 2 SVC.
The following constraint set(s) invoked at 2045 hrs 05/08/2025
S-SE_VC1
This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA
Refer to the AEMO Network Outage Scheduler for further information.
Manager NEM Real Time Operations
Cancellation - AEMO Intervention Event - SA region 02/08/2025
Cancellation - AEMO Intervention Event - SA region 02/08/2025
Refer to Market Notice 128424
The AEMO Intervention Event and all associated directions are cancelled from 1430 hrs on 05/08/2025.
Manager NEM Real Time Operations
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Cancellation: Direction issued to: AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128432
Direction is cancelled from: 1430 hrs 05/08/2025
Manager NEM Real Time Operations
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Update Direction - AGL SA Generation Pty Limited - TORRB2 TORRENS ISLAN
Refer to Market Notice 128427
The TORRB2 TORRENS ISLAN direction is now expected to stay in place until 1430 hrs 05/08/2025.
The direction update is issued at 1600 hrs 04/08/2025.
Manager NEM Real Time Operations