128160POWER SYSTEM EVENTS18/07/2025 08:49:29 AM

Non-credible contingency event - QLD region - 18/07/2025

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - QLD region - 18/07/2025

At 0825 hrs the H11_Nebo 275/132 kV No.1 Transformer was switched out on a planned outage and the H11_Nebo 275 kV SVC tripped.

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage.

Manager NEM Real Time Operations
     
128159NON-CONFORMANCE18/07/2025 06:30:29 AM

NON-CONFORMANCE Region QLD1 Friday, 18 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Friday, 18 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: DDPS1
Duration: 18/07/2025 06:25 to 18/07/2025 06:30
Amount: -14 MW
Constraint: NC-Q_DDPS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128135RESERVE NOTICE16/07/2025 05:11:13 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 16/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1800 hrs 16/07/2025 to 1900 hrs 16/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1343 MW.


Manager NEM Real Time Operations
     
128133NON-CONFORMANCE16/07/2025 07:20:23 AM

NON-CONFORMANCE Region QLD1 Wednesday, 16 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE QLD1 Region Wednesday, 16 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: ULPBESS1
Duration: 16/07/2025 07:10 to 16/07/2025 07:20
Amount: 7 MW
Constraint: NC-Q_ULPBESS1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128119RESERVE NOTICE13/07/2025 01:42:17 PM

PDPASA - Cancellation of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 128118 is cancelled at 1338 hrs 13/07/2025.

Manager NEM Real Time Operations
     
128118RESERVE NOTICE13/07/2025 12:51:15 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 14/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following Period:


[1.] From 0800 hrs 14/07/2025 to 0930 hrs 14/07/2025.
The forecast capacity reserve requirement is 436 MW.
The minimum capacity reserve available is 325 MW.


Manager NEM Real Time Operations
     
128086NON-CONFORMANCE10/07/2025 08:45:11 AM

NON-CONFORMANCE Region NSW1 Thursday, 10 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Thursday, 10 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: WTAHB1
Duration: 10/07/2025 08:40 to 10/07/2025 08:45
Amount: 12 MW
Constraint: NC-N_WTAHB1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128063NON-CONFORMANCE09/07/2025 04:30:16 PM

NON-CONFORMANCE Region VIC1 Wednesday, 9 July 2025

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Wednesday, 9 July 2025

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: MOKOSF1
Duration: 09/07/2025 12:55 to 09/07/2025 16:30
Amount: 15 MW
Constraint: NC-V_MOKOSF1

Auto-generated on behalf of Manager NEM Real Time Operations
     
128013RESERVE NOTICE08/07/2025 04:46:59 PM

PDPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the NSW Region on 08/07/2025

AEMO ELECTRICITY MARKET NOTICE

AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following Period:


[1.] From 1730 hrs 08/07/2025 to 1800 hrs 08/07/2025.
The forecast capacity reserve requirement is 1400 MW.
The minimum capacity reserve available is 1392 MW.