STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the SA Region on 01/07/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
[1.] From 0630 hrs 01/07/2025 to 0800 hrs 01/07/2025.
The forecast capacity reserve requirement is 353 MW.
The minimum capacity reserve available is 292 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time at which it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127883 is cancelled at 2335 hrs. 27/06/2025.
No LOR2 condition is currently forecast in the STPASA period.
Manager NEM Real Time Operations
STPASA - Update of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127882 has been updated at 2030 hrs. 27/06/2025 to the following:
[1.] From 1700 hrs. 30/06/2025 to 2000 hrs. 30/06/2025.
The forecast capacity reserve requirement is 1239 MW.
The minimum capacity reserve available is 1168 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following periods:
[1.] From 0730 hrs 30/06/2025 to 0800 hrs 30/06/2025.
The forecast capacity reserve requirement is 1177 MW.
The minimum capacity reserve available is 1167 MW.
[2.] From 1630 hrs 30/06/2025 to 1800 hrs 30/06/2025.
The forecast capacity reserve requirement is 1270 MW.
The minimum capacity reserve available is 1109 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
Manager NEM Real Time Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 03/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following period:
From 0000 hrs to 0200 hrs 03/07/2025.
The forecast capacity reserve requirement is 460 MW.
The minimum capacity reserve available is 355 MW.
AEMO Operations
STPASA - Update of the Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 02/07/2025
The Forecast LOR1 condition in the SA region advised in AEMO Electricity Market Notice No. 127872 has been updated at 1400 hrs 27/06/2025 to the following:
1. From 0000 hrs to 1030 hrs 02/07/2025.
The forecast capacity reserve requirement is 454 MW.
The minimum capacity reserve available is 325 MW.
2. From 1630 hrs to 2359 hrs 02/07/2025.
The forecast capacity reserve requirement is 457 MW.
The minimum capacity reserve available is 315 MW.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 1 (LOR1) in the SA Region on 01/07/2025
AEMO declares a Forecast LOR1 condition under clause 4.8.4(b) of the National Electricity Rules for the SA region for the following periods:
1. From 0600 hrs to 1000 hrs 01/07/2025.
The forecast capacity reserve requirement is 448 MW.
The minimum capacity reserve available is 335 MW.
2. From 1630 hrs to 2359 hrs 01/07/2025.
The forecast capacity reserve requirement is 454 MW.
The minimum capacity reserve available is 325 MW.
AEMO Operations
STPASA - Cancellation of the Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025
The Forecast LOR2 condition in the NSW region advised in AEMO Electricity Market Notice No. 127876 is cancelled at 1100 hrs 27/06/2025.
No LOR2 condition is currently forecast in the STPASA period.
AEMO Operations
STPASA - Forecast Lack Of Reserve Level 2 (LOR2) in the NSW Region on 30/06/2025
AEMO declares a Forecast LOR2 condition under clause 4.8.4(b) of the National Electricity Rules for the NSW region for the following period:
From 0730 hrs to 0800 hrs 30/06/2025.
The forecast capacity reserve requirement is 1241 MW.
The minimum capacity reserve available is 828 MW.
AEMO is seeking a market response.
AEMO has not yet estimated the latest time it would need to intervene through an AEMO intervention event.
AEMO Operations