75762RECLASSIFY CONTINGENCY20/05/2020 01:44:30 AM

Cancellation of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV

Cancellation time: 20/05/2020 01:44

Constraint set(s) revoked:
F-T-FASH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-FASH_N-2_CP4_S3 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 75756

Auto-generated on behalf of Manager NEM Real Time Operations
75761RECLASSIFY CONTINGENCY20/05/2020 01:44:30 AM

Cancellation of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Cancellation time: 20/05/2020 01:44

Constraint set(s) revoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Refer AEMO Electricity Market Notice 75755

Auto-generated on behalf of Manager NEM Real Time Operations
75760RECLASSIFY CONTINGENCY20/05/2020 01:36:01 AM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 20/05/2020 01:35 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
75759RECLASSIFY CONTINGENCY20/05/2020 01:19:50 AM

Cancellation of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Cancellation time: 20/05/2020 01:19

Constraint set(s) revoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 75758

Auto-generated on behalf of Manager NEM Real Time Operations
75758RECLASSIFY CONTINGENCY20/05/2020 12:17:40 AM

Reclassification of a Non-Credible Contingency Event: Hazelwood - Rowville No.1 220kV line and Hazelwood - Rowville No.2 220kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Hazelwood - Rowville No.1 220kV and Hazelwood - Rowville No.2 220kV

Duration: 20/05/2020 00:17 until further notice

Constraint set(s) invoked:
V-HWRO_R_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
75757RECLASSIFY CONTINGENCY19/05/2020 10:43:25 PM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 19/05/2020 22:43 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
75756RECLASSIFY CONTINGENCY19/05/2020 10:43:25 PM

Reclassification of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV

Duration: 19/05/2020 22:43 until further notice

Constraint set(s) invoked:
F-T-FASH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-FASH_N-2_CP4_S3 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Auto-generated on behalf of Manager NEM Real Time Operations
75755RECLASSIFY CONTINGENCY19/05/2020 10:43:25 PM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 19/05/2020 22:43 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
75754INTER-REGIONAL TRANSFER19/05/2020 05:41:53 PM

Inter-Regional Transfer Limit Variation Taree-Port Macquarie 964 132 kV Transmission line - NSW Region. - 19/05/2020

AEMO ELECTRICITY MARKET NOTICE

Inter-Regional Transfer Limit Variation - Taree -Port Macquarie 964 132 kV Transmission line - NSW Region.
At 17:35 there has been a short notice outage of Taree - Port Macquarie 964 132 kV Transmission line.

The following constraint set was invoked at 1740 hrs 19/05/2020.
N-TAPM_964

The constraint set contains the following interconnector on the left hand side.

N-Q-MNSP1
NSW1-QLD1

See AEMO Network Outage Scheduler (NOS) for details.