75975RECLASSIFY CONTINGENCY14/06/2020 09:19:17 AM

Cancellation of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: QLD1

Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV

Cancellation time: 14/06/2020 09:19

Constraint set(s) revoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1


Refer AEMO Electricity Market Notice 75973

Auto-generated on behalf of Manager NEM Real Time Operations
75974POWER SYSTEM EVENTS14/06/2020 08:40:54 AM

Non-credible contingency event - VIC region - 14/06/2020

AEMO ELECTRICITY MARKET NOTICE.

Non-credible contingency event - VIC region - 14/06/2020

At 0647 hrs the Eildon - Mt Beauty 1 220 kV Line tripped at Eildon end only..

AEMO did not instruct load shedding.

AEMO has not been advised of any disconnection of bulk electrical load.

The cause of this non credible contingency event is not known at this stage and is under investigation.

Manager NEM Real Time Operations
75973RECLASSIFY CONTINGENCY14/06/2020 06:18:20 AM

Reclassification of a Non-Credible Contingency Event: Bulli Creek - Dumaresq 8L 330KV line and Bulli Creek - Dumaresq 8M 330KV line in QLD1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: QLD1

Lines: Bulli Creek - Dumaresq 8L 330KV and Bulli Creek - Dumaresq 8M 330KV

Duration: 14/06/2020 06:18 until further notice

Constraint set(s) invoked:
I-QNI_ONE_PHASE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
NSW1-QLD1


Auto-generated on behalf of Manager NEM Real Time Operations
75972RECLASSIFY CONTINGENCY14/06/2020 12:49:17 AM

Cancellation of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Cancellation time: 14/06/2020 00:49

Constraint set(s) revoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Refer AEMO Electricity Market Notice 75971

Auto-generated on behalf of Manager NEM Real Time Operations
75971RECLASSIFY CONTINGENCY13/06/2020 11:46:07 PM

Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Duration: 13/06/2020 23:46 until further notice

Constraint set(s) invoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
75970RECLASSIFY CONTINGENCY13/06/2020 11:09:15 PM

Cancellation of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Cancellation time: 13/06/2020 23:09

Constraint set(s) revoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Refer AEMO Electricity Market Notice 75969

Auto-generated on behalf of Manager NEM Real Time Operations
75969RECLASSIFY CONTINGENCY13/06/2020 09:06:52 PM

Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 220 kV line and Dederang - Glenrowan No.3 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 220 kV and Dederang - Glenrowan No.3 220 kV

Duration: 13/06/2020 21:06 until further notice

Constraint set(s) invoked:
V-DDGN_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
75968RECLASSIFY CONTINGENCY13/06/2020 05:05:21 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Para-Templers West and Magill-Torrens Island A 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Para-Templers West and Magill-Torrens Island A 275kV lines

Cancellation time: 1700 hrs 13/06/2020

Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 75960

Manager NEM Real Time Operations
75967RECLASSIFY CONTINGENCY13/06/2020 05:04:58 PM

Cancellation of the reclassification of a Non-Credible Contingency Event: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines in SA due to severe weather warning.

AEMO ELECTRICITY MARKET NOTICE.

Cancellation of the reclassification of a non-credible contingency event as a credible contingency event due to severe weather warning.

AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any severe weather warning in the vicinity of the following lines. Accordingly, its classification has reverted to a non-credible contingency event.

Region: SA

Lines: Brinkworth-Davenport, Brinkworth-Templers West and Para-Templers West 275kV lines

Cancellation time: 1700 hrs 13/06/2020

Constraint set(s) revoked: Nil

Refer AEMO Electricity Market Notice 75959