Market Notices

79966NON-CONFORMANCE16/11/2020 02:00:17 AM

NON-CONFORMANCE Region SA1 Monday, 16 November 2020

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 16 November 2020

AEMO declared a schedule generating unit non-conforming

Unit: LKBONNY3
Duration: 16/11/2020 01:25 to 16/11/2020 02:00
Amount: 12 MW
Constraint: NC-S_LKBONNY3

Auto-generated on behalf of Manager NEM Real Time Operations
79965RECLASSIFY CONTINGENCY16/11/2020 01:58:56 AM

Reclassification of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV

Duration: 16/11/2020 01:20 until further notice

Constraint set(s) invoked:

T-FASH_N-2_CP4_S5A Constraint set contains the following interconnector(s) on the left hand side: NONE


Auto-generated on behalf of Manager NEM Real Time Operations
79964RECLASSIFY CONTINGENCY16/11/2020 01:57:35 AM

Reclassification of a Non-Credible Contingency Event: Dederang - Glenrowan No.1 & No.3 220 kV Lines line and Numurkah Solar Farm line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Dederang - Glenrowan No.1 & No.3 220 kV Lines and Numurkah Solar Farm

Duration: 16/11/2020 01:57 until further notice

Constraint set(s) invoked:
V-NIL_DDGN_NSF_N-2 Constraint set contains the following interconnector(s) on the left hand side:
V-S-MNSP1
VIC1-NSW1


Auto-generated on behalf of Manager NEM Real Time Operations
79963RECLASSIFY CONTINGENCY16/11/2020 01:51:10 AM

Reclassification of a Non-Credible Contingency Event: Eildon PS - Mt Beauty No.1 220 kV line and Eildon PS - Mt Beauty No.2 220 kV line in VIC1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: VIC1

Lines: Eildon PS - Mt Beauty No.1 220 kV and Eildon PS - Mt Beauty No.2 220 kV

Duration: 16/11/2020 01:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
79962RECLASSIFY CONTINGENCY16/11/2020 01:51:10 AM

Reclassification of a Non-Credible Contingency Event: Farrell-John Butters line and Farrell-Rosebery-Newton-Queenstown line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell-John Butters and Farrell-Rosebery-Newton-Queenstown

Duration: 16/11/2020 01:51 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
79961NON-CONFORMANCE16/11/2020 01:50:11 AM

NON-CONFORMANCE Region SA1 Monday, 16 November 2020

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE SA1 Region Monday, 16 November 2020

AEMO declared a schedule generating unit non-conforming

Unit: LKBONNY2
Duration: 16/11/2020 01:20 to 16/11/2020 01:50
Amount: 44 MW
Constraint: NC-S_LKBONNY2

Auto-generated on behalf of Manager NEM Real Time Operations
79960RECLASSIFY CONTINGENCY16/11/2020 01:39:30 AM

Reclassification of a Non-Credible Contingency Event: Farrell - Reece No.1 220 kV line and Farrell - Reece No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Farrell - Reece No.1 220 kV and Farrell - Reece No.2 220 kV

Duration: 16/11/2020 01:39 until further notice

Constraint set(s) invoked:
F-T-FARE_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1


Auto-generated on behalf of Manager NEM Real Time Operations
79959RECLASSIFY CONTINGENCY16/11/2020 01:26:30 AM

Reclassification of a Non-Credible Contingency Event: Sheffield - Wesley Vale 110kV line and Sheffield - Devonport 110kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits to now be more likely and reasonably possible. Accordingly AEMO has reclassified it as a credible contingency event.

Region: TAS1

Lines: Sheffield - Wesley Vale 110kV and Sheffield - Devonport 110kV

Duration: 16/11/2020 01:26 until further notice

Constraint set(s) invoked:
NONE

Auto-generated on behalf of Manager NEM Real Time Operations
79958RECLASSIFY CONTINGENCY16/11/2020 01:20:15 AM

Cancellation of a Non-Credible Contingency Event: Farrell-Sheffield No.1 220 kV line and Farrell-Sheffield No.2 220 kV line in TAS1 due to Lightning.

AEMO ELECTRICITY MARKET NOTICE

Cancellation of reclassification of a Non-Credible Contingency Event as a Credible Contingency Event due to Lightning. AEMO considers the simultaneous trip of the following circuits is no longer reasonably possible. There is no longer any lightning activity in the vicinity of the following lines. Accordingly its classification has reverted to a non-credible contingency event.

Region: TAS1

Lines: Farrell-Sheffield No.1 220 kV and Farrell-Sheffield No.2 220 kV

Cancellation time: 16/11/2020 01:20

Constraint set(s) revoked:
F-T-FASH_N-2 Constraint set contains the following interconnector(s) on the left hand side:
T-V-MNSP1
T-FASH_N-2_CP4_S3 Constraint set contains the following interconnector(s) on the left hand side:
NONE


Refer AEMO Electricity Market Notice 79957

Auto-generated on behalf of Manager NEM Real Time Operations