Market Notices

116446GENERAL NOTICE02/05/2024 07:49:28 PM

Network Augmentation Commissioned - QLD Region - 02/05/2024

AEMO ELECTRICITY MARKET NOTICE

Network Augmentation Commissioned - QLD Region - 02/05/2024

Commissioned:

H13 Ross - H93 Guybal Munjan No.8917 275 kV line

Manager NEM Real Time Operations
     
116375NON-CONFORMANCE29/04/2024 08:55:22 PM

NON-CONFORMANCE Region NSW1 Monday, 29 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE NSW1 Region Monday, 29 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: VP5
Duration: 29/04/2024 20:50 to 29/04/2024 20:55
Amount: -18 MW
Constraint: NC-N_VP5

Auto-generated on behalf of Manager NEM Real Time Operations
     
116369NON-CONFORMANCE29/04/2024 01:05:16 PM

NON-CONFORMANCE Region VIC1 Monday, 29 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Monday, 29 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: JLB01
Duration: 29/04/2024 13:00 to 29/04/2024 13:05
Amount: 35 MW
Constraint: NC-V_JLB01

Auto-generated on behalf of Manager NEM Real Time Operations
     
116346INTER-REGIONAL TRANSFER27/04/2024 08:41:29 AM

Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Dapto - Marulan No. 8 330 kV Line - NSW region - 27/04/2024

At 0830 hrs 27/04/2024 there was a short notice outage of Dapto - Marulan No. 8 330 kV Line.

Constraint set(s) invoked: N-DTMN_8_15M

This constraint set contains equations with the following interconnectors on the LHS.

N-Q-MNSP1
NSW1-QLD1
VIC1-NSW1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116345NON-CONFORMANCE26/04/2024 10:45:22 PM

NON-CONFORMANCE Region VIC1 Friday, 26 April 2024

AEMO ELECTRICITY MARKET NOTICE

NON-CONFORMANCE VIC1 Region Friday, 26 April 2024

AEMO has declared the following unit as non-conforming under clause 3.8.23 of the National Electricity Rules:

Unit: YWPS3
Duration: 26/04/2024 22:40 to 26/04/2024 22:45
Amount: 17 MW
Constraint: NC-V_YWPS3

Auto-generated on behalf of Manager NEM Real Time Operations
     
116329GENERAL NOTICE25/04/2024 11:56:40 AM

Planned outage of Gordon - Chapel St No. 1 220 kV line in the TAS region on 26/04/2024

AEMO ELECTRICITY MARKET NOTICE

The Gordon - Chapel St No. 1 220 kV line in the Tasmania (TAS) region is planned to be out of service from 1030 hrs on 26/04/2024 to 1500 hrs on 26/04/2024

A credible contingency event during this planned outage could cause a large reduction in generation in TAS.

Refer AEMO Network Outage Schedule (NOS) for further details.

Manager NEM Real Time Operations
     
116275INTER-REGIONAL TRANSFER23/04/2024 08:52:22 AM

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Para No 1 SVC - SA region - 23/04/2024

At 0837 hrs 23/04/2024 there was an unplanned outage of Para No 1 SVC.

Constraint set(s) invoked: S-PA_VC1


This constraint set(s) contains equations with the following interconnectors on the LHS.
V-SA,V-S-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     
116272INTER-REGIONAL TRANSFER22/04/2024 02:55:17 PM

Inter-regional transfer limit variation -Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Liddell - Tomago 82 330kV Line - NSW region - 22/04/2024

A planned outage of Liddell - Tomago 82 330kV Line in the NSW region was scheduled from 0600 hrs 03/04/2024 to 1700 hrs 22/04/2024.

The outage has been completed and Liddell - Tomago 82 330kV Line returned to service at 1450 hrs 22/04/2024

Constraint set(s) revoked: N-LDTM_82_OPEN

Manager NEM Real Time Operations
     
116270INTER-REGIONAL TRANSFER22/04/2024 01:32:54 PM

Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024

AEMO ELECTRICITY MARKET NOTICE

Inter-regional transfer limit variation - Farrell - Sheffield Nos 1 and 2 220kV Lines - TAS region - 22/04/2024

At 1315 hrs 22/04/2024 there was an unplanned outage of Farrell - Sheffield Nos 1 and 2 220kV Lines.

The following constraint set(s) invoked at 1315 hrs 22/04/2024
T-X_FASH_C

This constraint set(s) contains equations with the following interconnectors on the LHS.
T-V-MNSP1

Refer to the AEMO Network Outage Scheduler for further information.

Manager NEM Real Time Operations
     